Mumbai/Project record

MahaRERA · the public record

Darshan Lifestyle - Tanishq D wing and E wing

Vangaon West · Parks Developers LLP

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
31 Dec 2023declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for Darshan Lifestyle - Tanishq D wing and E wing

MahaRERA · P99000013757

Delivery and registration

When is the project declared for completion?

Darshan Lifestyle - Tanishq D wing and E wing is registered with MahaRERA as P99000013757 and the promoter has declared completion for 31 Dec 2023.

31 Dec 2023

declared completion

34months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP99000013757
Registered on25 Oct 2017
Promoter-declared completion31 Dec 2023
Current statusCertificate Signed
Against todayabout 34 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Darshan Lifestyle - Tanishq D wing and E wing record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Promoter record

What else is this promoter on record for?

Parks Developers LLP is the promoter of record on 2 projects registered with MahaRERA.

2projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Darshan Lifestyle - Tanishq D wing and E wing in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
Tanishq D Wing1G+431 Oct 2020
Tanishq E Wing1G+431 Oct 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Apr 2022Project execution affected a lot due to Lockdwon & recovery period post lockdown. But now works are in full swing & project will be completed within this extended deadline.
30 Apr 202231 Dec 2023Project execution affected a lot due to Lockdwon & recovery period post lockdown. But now works are in full swing & project will be completed within this extended deadline.

Location, Land & Connectivity

Located at Vangaon West, Vangaon, Mumbai City, Mumbai City, 401103. Per the filed land record, the plot is bounded to the north by Darshan Lifestyle Building Type F2 anf E2, to the south by Darshan Lifestyle Building Type H I and J, to the east by Internal Road of Darshan Lifestyle and to the west by Darshan Lifestyle Building Type F1. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 84 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Andheri MIDC / SEEPZ84 km
Powai / Hiranandani business park86 km
Chhatrapati Shivaji Int'l Airport88 km
Bandra Kurla Complex (BKC)91 km
Lower Parel / Worli business district98 km
Nariman Point / Fort106 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Vangaon

Ekta Parksville Phase II
declared completion Dec 2026 · Ekta Parksville Homes Pvt. Ltd.
Galaxy Residency
Not filing quarterly progress reports · declared completion Dec 2026 · Mahashakti Enterprises
Tanishq H AND I Wing
declared completion Dec 2026 · Puneet Developers
Ivory Homes
declared completion Jul 2027 · Yashron Developers LLP
Prime ONE
declared completion Dec 2027 · Primeville Developers LLP
Tanishq Type G-5,e-5,f-5 Wing P,q,r
declared completion Dec 2027 · Rajvan Lifespaces LLP
More projects in Palghar

Other RERA-registered projects in Palghar

Darshan Swapnalok Phase 2
declared completion Jan 2029 · Intelligent Landmarks LLP
Darshan Swapnalok Phase 3
declared completion Aug 2031 · Purehomes Lifespaces LLP
Datta Vihar
declared completion Dec 2028 · VED Samarth
Dattachhaya
declared completion Nov 2026 · Jagdish Manohar Mhatre
Dattani Linear Building No.3 Wing ABC Phase-II
declared completion Jun 2026 · Brijesh Satish Dattani
Dattani Vertex Building No.4 Wing AB Phase-II
declared completion Jun 2026 · Brijesh Satish Dattani

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.