Mumbai/Project record

MahaRERA · the public record

Devnagri flower city phase 1

RASSAYANI · MAHARASHTRA CONSTRUCTION COMPANY

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Dec 2023declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for Devnagri flower city phase 1

MahaRERA · P52000015138

Delivery and registration

When is the project declared for completion?

Devnagri flower city phase 1 is registered with MahaRERA as P52000015138 and the promoter has declared completion for 30 Dec 2023.

30 Dec 2023

declared completion

34months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP52000015138
Registered on02 Feb 2018
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 34 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Devnagri flower city phase 1 record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Devnagri flower city phase 1 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+44.

BuildingWingsFloorsDeclared completion
building no 11G+4431 Dec 2022
bulding no 21G+2431 Dec 2022
building no 41G+1431 Dec 2022
building no 51G+1231 Dec 2022

Legal and disputes

What disputes are disclosed?

18 complaints are on the MahaRERA record for Devnagri flower city phase 1, with orders passed in 18 of them.

18complaints

18with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000002325706/02/2018Ajay Jeya Nadar vs Shanup S.Dhariaorder passed
CC00600000005648909/10/2018RAVI SHANKAR PRASAD vs Shree Santosh Kumar J.Singhorder passed
CC00600000007894622/04/2019SANTOSH C RANE vs SANTOSH SINGHorder passed
CC00600000007894822/04/2019PRAVIN R BODAKE vs SANTOSH SINGHorder passed
CC00600000039726303/10/2023Avinash Dayaram Ratne vs MS. MAHARASHTRA CONSTRUCTION COMPANYorder passed
CC00600000039763303/10/2023MALLESH GOVIND NAIDU vs MS.MAHARASHTRA CONSTRUCTION COMPANYorder passed
CC00600000039768208/10/2023UMASHANKAR HARILAL PAL vs MS.MAHARASHTRA CONSTRUCTION COMPANYorder passed
CC00600000039763103/10/2023DIPTI GUPTA vs MS.MAHARASHTRA CONSTRUCTION COMPANYorder passed
CC00600000039750316/09/2023Shobhit Agarwal vs SANTOSH KUMAR JAIPRAKASH SINGHorder passed
CC00600000039762315/10/2023Medha Sudhakar Nate vs MS. MAHARASHTRA CONSTRUCTION COMPANYorder passed
CC00600000039768108/10/2023Dattatray Nagorao kamble vs MS. MAHARASHTRA CONSTRUCTION COMPANYorder passed
CC00600000039765715/10/2023Rizwan Hashmatullah Quraishi vs MS. MAHARASHTRA CONSTRUCTION COMPANYorder passed
CC00600000039764305/10/2023RAHUL JALBA BANSODE vs MS. MAHARASHTRA CONSTRUCTION COMPANYorder passed
CC00600000039765805/10/2023GAUTAM KUMAR DAS vs MS. MAHARASHTRA CONSTRUCTION COMPANYorder passed
CC00600000039768318/11/2023SAYED FEROZ AHMED GOUSODDIN INAMDAR vs MS. MAHARASHTRA CONSTRUTION COMPANYorder passed
CC00600000039776718/11/2023VIJAYKUMAR CHANGARANGATH vs MS. MAHARASHTRA CONSTRUCTION COMPANYorder passed
CC00600000048021824/04/2024Mahesh Kumar Das vs 1. Vedant Realtors, 2. Santosh Singh, 3. Ajay Jayaorder passed
CC00600000053070916/08/2024DHONDU VASANT GAWADE vs AJAY JEYAMURGAN NADARorder passed

Location, Land & Connectivity

Located at RASSAYANI, PEN - APTA ROAD, Panvel, Raigarh, 410206. Per the filed land record, the plot is bounded to the north by Open space, to the south by Open space, to the east by Open space and to the west by Open space. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 37 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Nariman Point / Fort37 km
Bandra Kurla Complex (BKC)37 km
Lower Parel / Worli business district38 km
Powai / Hiranandani business park38 km
Chhatrapati Shivaji Int'l Airport39 km
Andheri MIDC / SEEPZ42 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Panvel

Shreeji Icon
declared completion Oct 2026 · Shreeji Lifespaces Group
Govind Ameya
declared completion Oct 2026 · Mansarovar Constructions
Shikara Greens Phase I
declared completion Oct 2026 · Shikara Constructions Pvt. Ltd.
Ambers Dnyaneshwar Capital
declared completion Nov 2026 · Capital Builders
Govind Greens
declared completion Nov 2026 · Priyal Buildcon LLP
Jupiter Royal
declared completion Nov 2026 · Arjun Ashok Tarachandani
More builders in Panvel

Major developers building in Panvel

More projects in Raigarh

Other RERA-registered projects in Raigarh

Devpriya
declared completion Jun 2027 · Shree Chamunda Realty
Devta Vision Ganaranga Paradise
declared completion Oct 2026 · Devta Vision Developers LLP
Devta Vision Sukhkarta Apartment
declared completion Oct 2026 · Devta Vision Developers LLP
Dhanalaxmi
declared completion Dec 2022 · Parag Pankaj Thakker
Dhanashree Apartment
declared completion Apr 2028 · Shree Ekvira Developers LLP
Dhanashree Apartment
declared completion Dec 2025 · Manunayak Manshing Rathlavath

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.