Mumbai/Project record

MahaRERA · the public record

GALAXY APARTMENT

Palghar · ARIF RAZAK MEMON

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Dec 2021declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for GALAXY APARTMENT

MahaRERA · P99000011907

Delivery and registration

When is the project declared for completion?

GALAXY APARTMENT is registered with MahaRERA as P99000011907 and the promoter has declared completion for 30 Dec 2021.

30 Dec 2021

declared completion

58months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP99000011907
Registered on31 Aug 2017
Promoter-declared completion30 Dec 2021
Current statusCertificate Signed
Against todayabout 58 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for GALAXY APARTMENT record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for GALAXY APARTMENT in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3.

BuildingWingsFloorsDeclared completion
GALAXY APARTMENT WING A1G+3-
GALAXY APARTMENT WING B1G+3-
GALAXY APARTMENT WING C1G+3-

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for GALAXY APARTMENT, with orders passed in 2 of them.

2complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC1250240515/07/2025ALLAN DBRITTO vs ARIF RAZAK MEMONorder passed
CC1250303228/08/2025ABRAR AKBAR SHAIKH vs ARIF RAZAK MEMONorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2021The project was halted due to certain reasons beyond our control and then this year it was further affected due to corona pandemic. Now the work is in progress & the project will b

Location, Land & Connectivity

Located at Vasai, Palghar, 401501. Per the filed land record, the plot is bounded to the north by SURVEY NO 21, to the south by SURVEY NO 74 HISSA NO 2, to the east by SURVEY NO 74 HISSA NO 3 and to the west by SURVEY NO 74 HISSA NO 2. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 75 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Andheri MIDC / SEEPZ75 km
Powai / Hiranandani business park77 km
Chhatrapati Shivaji Int'l Airport79 km
Bandra Kurla Complex (BKC)82 km
Lower Parel / Worli business district89 km
Nariman Point / Fort97 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Boisar

Marathe Complex
declared completion Dec 2026 · Gprs Realty
Rajhans United Regency III
declared completion Dec 2026 · Rajhans Homes
Yash Padma
declared completion Dec 2026 · SAI Shraddha Enterprises
Avani Residency
declared completion Dec 2026 · Avani Residency
Avasar Residency
declared completion Dec 2026 · Amico Builder
Bhakti Apartment Phase II
declared completion Dec 2026 · Saryu Builders & Developers
More projects in Palghar

Other RERA-registered projects in Palghar

Galaxy Apartment
declared completion Dec 2025 · ACE Developers
Galaxy Complex
declared completion Jul 2026 · Ksquare Realty Private Limited
Galaxy Complex
declared completion Jan 2026 · Ksquare Realty Private Limited
Galaxy Emperia Phase-1
declared completion Dec 2025 · Galaxy Shine Developers
Galaxy Emperia Phase-II
declared completion Jun 2028 · Galaxy Shine Developers
Galaxy Garden - II
declared completion Mar 2031 · Asian Builders And Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.