Project RERA record · Mumbai, Thane & the MMR

Hill Crest

by Universal Infra · MahaRERA P51700030982 · Certificate Signed · declared completion Sep 2024

Past its declared completion date

Past its declared completion date. Thane · ULHASNAGAR

Past its declared completion date

The developer's declared completion date has passed on the MahaRERA register. The project may have completed late or may still be under construction — the register flags the declared timeline, not actual handover.

Hill Crest is on MahaRERA's list of projects past their declared completion date. The register flags the declared timeline — the project may have completed late, may still be under construction, or may have obtained a RERA extension. The most direct check is to contact the developer for the current status and any revised RERA-filed timeline.

Other RERA-registered projects in Ulhasnagar

Atlanta Crown
Atlanta Construction
Atlanta Jewel
Shree SAI Samarth Developers LLP
Bramha Premsagar
Bramha Lifespaces

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Request the report on Hill Crest

We analyse Hill Crest in full and send you the RERA Property Intelligence Report — we analyse in 1 working day.

Something went wrong — email hello@quietlist.in instead.

Free · Risk Snapshot + alerts

The regulatory risk spine for Hill Crest, emailed as a clean scorecard — plus an alert if the RERA status changes:

  • 🔴  Past its declared completion date

Something went wrong — email hello@quietlist.in.

✓ On its way to your inbox — plus alerts if the status changes.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 11 Jul 2026