Mumbai/Project record

MahaRERA · the public record

Hive suites

Dadar · Shree Richa Realtors

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

30 Jun 2027declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗

Free project details

Registration read 18 Jul 2026

RERA details for Hive suites

MahaRERA · P51900012718

Delivery and registration

When is the project declared for completion?

Hive suites is registered with MahaRERA as P51900012718 and the promoter has declared completion for 30 Jun 2027.

30 Jun 2027

declared completion

8months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51900012718
Registered on07 Sep 2017
Promoter-declared completion30 Jun 2027
Current statusCertificate Signed
Against today8 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Hive suites record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (2025-06-30).

Prices filed in the CA certificate

8 sold or booked entries in this project’s CA certificate carry a filed agreement/allotment consideration and carpet area. The report includes the dated source record and its complete transcribed spreadsheet.

CA certificate dated 2024-07-12; reporting cutoff not established; downloaded from MahaRERA 2026-10-11.

These are amounts stated in the certificate, not independently verified sale deeds or cash collected. This table does not establish current unsold inventory.

See the Sales Report →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+24.

BuildingWingsFloorsDeclared completion
Hive Suites1G+2430 Dec 2022

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for Hive suites, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC1250424201/12/2025RANJANA PEDNEKAR vs Shree Richa Realtorsorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2027Due to Company financial and COVID project was delay we would request you to approve the extension as we have arrange fund

Location, Land & Connectivity

Located at Dadar, Gokhale Road, Mumbai City, Mumbai City, 400028. Per the filed land record, the plot is bounded to the north by CS no 1782 and 310, to the south by CS no 1587, to the east by Shivaji park road and to the west by Ranade road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 3 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Lower Parel / Worli business district3 km
Bandra Kurla Complex (BKC)6 km
Chhatrapati Shivaji Int'l Airport8 km
Nariman Point / Fort11 km
Andheri MIDC / SEEPZ12 km
Powai / Hiranandani business park13 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dadar West

Sugee Sukrut
declared completion Oct 2026 · Sugee Nine Developers LLP
1891 Ekam Parkk
declared completion Dec 2026 · Nascent Developers
Cynthiandra
declared completion Dec 2026 · Shubh Laxmi Developers
Shree SAI Arti
declared completion Dec 2026 · V.K Developers
Sigma Garnet
declared completion Dec 2026 · Colo Color Private Limited
Amara
declared completion Dec 2026 · Sharcon Mutha
More builders in Dadar West

Major developers building in Dadar West

More projects in Mumbai City

Other RERA-registered projects in Mumbai City

Horizon Tower
declared completion Oct 2020 · Horizon Realty
Hubtown - Celeste
declared completion Jul 2029 · Nayan Real Estate Private Limited
Hubtown Harmony A Wing
declared completion Dec 2024 · Heet Builders Private Limited
Hubtown Harmony B Wing
declared completion Dec 2024 · Heet Builders Private Limited
Hubtown Harmony Retail
declared completion Dec 2023 · Heet Builders Private Limited
Hubtown Vedant- 14th To 18th Floor
declared completion Dec 2025 · Citywood Builders Private Limited

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.