Mumbai/Project record

MahaRERA · the public record

JHALAK FOURWINGS

Sai Section · JHALAK CONSTRUCTIONS

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
31 Dec 2031declared completionMahaRERA registration · read 19 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 19 Jul 2026

Free project details

Registration read 19 Jul 2026

RERA details for JHALAK FOURWINGS

MahaRERA · P51700047861

Delivery and registration

When is the project declared for completion?

JHALAK FOURWINGS is registered with MahaRERA as P51700047861 and the promoter has declared completion for 31 Dec 2031.

31 Dec 2031

declared completion

62months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 19 Jul 2026

MahaRERA registrationP51700047861
Registered on28 Nov 2022
Promoter-declared completion31 Dec 2031
Current statusCertificate Signed
Against today62 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for JHALAK FOURWINGS record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 19 Jul 2026

View the free 14-item checklist →

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (2025-06-30).

Promoter record

What else is this promoter on record for?

JHALAK CONSTRUCTIONS is the promoter of record on 6 projects registered with MahaRERA.

6projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 19 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for JHALAK FOURWINGS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 19 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
Building 11G+831 Dec 2031
Building 21G+831 Dec 2031
Building 31G+831 Dec 2031
Building 41G+831 Dec 2031

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Sai Section, Sai Section, Ulhasnagar, Thane, 421501. Per the filed land record, the plot is bounded to the north by Road to the south, to the south by Road to the east, to the east by Building to west open plot and to the west by Building. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Ambernath

Meera Nanda Bliss
declared completion Nov 2026 · Meera Homes LLP
Raj Residency
declared completion Nov 2026 · Vijay Chahu Patil
Precious Empire Wing A, B AND C
declared completion Dec 2026 · RKR Reality
Chaitraban CHS
declared completion Dec 2026 · Annapurna Enterprises
Dipti Skycity Bldg No. 7
declared completion Dec 2026 · Dipti Home Makers Pvt Ltd
Imperial Heights
declared completion Dec 2026 · Krishna Developers
More builders in Ambernath

Major developers building in Ambernath

More projects in Thane

Other RERA-registered projects in Thane

Jhalak Hillock
declared completion Dec 2027 · Jhalak Constructions
Jhalak Palacia
declared completion Dec 2028 · Jhalak Constructions
Jhalak Paradise
declared completion Dec 2025 · Jhalak Constructions
Jignesh CO. OP. Hsg. Society. LTD
declared completion Apr 2028 · Shree Atharva Apex
Jijai Apartment
declared completion Sep 2025 · Shree Balaji Developers
Jitesh Hill Crest
declared completion Dec 2028 · JAY Construction

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.