Mumbai/Project record

MahaRERA · the public record

KANDIVALI GEETA SADAN CHS LTD

Kandivali West · MS PRATHMESH LANDMARK CONSULTANCY

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

1units filed as unsoldInventory · 22 October 2026
30 Apr 2025declared completionMahaRERA registration · read 18 Jul 2026
45registered unitsMahaRERA registration · read 18 Jul 2026

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗

Free project details

Registration read 18 Jul 2026

RERA details for KANDIVALI GEETA SADAN CHS LTD

MahaRERA · P51800006861

Delivery and registration

When is the project declared for completion?

KANDIVALI GEETA SADAN CHS LTD is registered with MahaRERA as P51800006861 and the promoter has declared completion for 30 Apr 2025.

30 Apr 2025

declared completion

18months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51800006861
Registered on16 Aug 2017
Promoter-declared completion30 Apr 2025
Current statusCertificate Signed
Against todayabout 18 months past the declared date

Sales

How many are filed as sold or booked?

In KANDIVALI GEETA SADAN CHS LTD, 22 of 23 units filed with MahaRERA are recorded as sold or booked (19 with registered agreements and 3 booked), about 96%, and 1 are filed as unsold.

96%sold or booked

22 of 23 units

₹17.18 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹11.54 Cr (about 67%) is recorded as collected and ₹5.65 Cr as receivable. The registration lists 45 units; this inventory lists 23. These are separate filed records. Their counts do not match; neither count establishes today's availability.

Source · MahaRERA sold/unsold inventory filing · read 18 Jul 2026

Filed agreement values: across 22 sold or booked entries with usable filed values and areas, the effective carpet rate is ₹16,715/sqft, with eight in ten falling between ₹7,727 and ₹22,501 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the unit.

FloorUnitCarpetGovt reckoner value
Ground/Floor 01121 sqft (11.28 sqm)₹30.00 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, unit by unit

Read from MahaRERA on 22 October 2026

MahaRERA publishes, unit by unit, what this promoter filed: which units are sold and which are not, the RERA carpet area of each, and for sold or booked entries the filed agreement value — the consideration filed for that specific unit. On this project 22 units carry one, and 1 of the 23 are recorded unsold.

A filed consideration is the amount the promoter reported for one unit. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the unit is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

In KANDIVALI GEETA SADAN CHS LTD, 0 of the 1 unsold units have filed sales to compare with. The Sales Report gives each of them its own row — the filed agreements behind its comparison listed in full, the government reckoner value the promoter filed against it, and mortgage status where the filing supplies it. Missing mortgage information is not confirmation that a unit is free of a mortgage. Built from the filing itself, sent by email.

See the other 1 unit — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8 and 45 units are registered across the project.

BuildingWingsFloorsUnitsDeclared completion
KANDIVALI GEETA SADAN CHS LTD1G+845-

Unit mix on the filing: 36 residential and 9 non-residential.

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for KANDIVALI GEETA SADAN CHS LTD, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000059102523/07/2024TULSI MINESHKUMAR SURA vs -order passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 4 times, as recorded on the register.

FromExtended toStated reason
as registered29 Jun 2020NON APPROVAL OF PLAN AS EXPLAINED BY OUR ARCHITECT THE DCPR 2034 SANCTIONED AND IMPLEMENTED FROM NOVEMBER 2018. THE PROCESS OF APPROVAL FOR ONGOING PROJECT STALLED DUE TO 1 CHANG
29 Jun 202030 Apr 2023DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED IN TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION FOR 30 MONTHS.
30 Apr 202330 Jun 2024DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 30/06/2024
30 Jun 202430 Apr 2025Contractor Management: Issues related to contractor management have also played a critical role in the delays. Problems include miscommunication among subcontractors, inadequate p

Location, Land & Connectivity

Located at Kandivali West, 0, Andheri, Mumbai Suburban, 400067. Per the filed land record, the plot is bounded to the north by SHANTILAL MODY ROAD, to the south by CTS NO 257, to the east by CTS NO 259 and to the west by HEMU KALANI ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 9 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Andheri MIDC / SEEPZ9 km
Powai / Hiranandani business park12 km
Chhatrapati Shivaji Int'l Airport13 km
Bandra Kurla Complex (BKC)16 km
Lower Parel / Worli business district23 km
Nariman Point / Fort31 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kandivali West

Goyal Aspire
declared completion Oct 2026 · Nexa Buildcon LLP
Kandivali Hanuman Co-Op Housing Society Ltd
declared completion Nov 2026 · Kandivali Hanuman Co-Op Housing Society
Avenue Wing B
declared completion Dec 2026 · Dharmesh Constructions Private Limited
RAM Chhaya
Not filing quarterly progress reports · declared completion Dec 2026 · Prime Infra
Rock Highland
declared completion Dec 2026 · Rock Estates
Sale Bldg NO. 6 Wing Known AS Northern Supremus & Northern Hills Building NO. 1 & 2
declared completion Dec 2026 · N.rose Developers PVT LTD
More projects in Mumbai Suburban

Other RERA-registered projects in Mumbai Suburban

Kandivali Hanuman Co-Op Housing Society Ltd
declared completion Nov 2026 · Kandivali Hanuman Co-Op Housing Society
Kandivali Jatin Villa Chsl
declared completion Feb 2026 · Mamtora Enterprise
Kandivali Matru Ashish Chsl
declared completion Jun 2028 · Shree Jalaram Builders & Developers
Kandivali Sanghvi CO-OP Housing Society LTD
declared completion Jun 2028 · Tamos Associates
Kanjur Matruchhaya CHS LTD
declared completion Jun 2022 · Sunil Dinkar Shinde
Kannamwar Nagar Datta Niwas
declared completion Dec 2026 · Vighnaharta Heights Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.