KAVYA ASHWAMEGH

MUMBAI · KAVYA CONSTRUCTION COMPANY

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
31 Dec 2024declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for KAVYA ASHWAMEGH

MahaRERA · P51800007183

Delivery and registration

When is the project declared for completion?

KAVYA ASHWAMEGH is registered with MahaRERA as P51800007183 and the promoter has declared completion for 31 Dec 2024.

31 Dec 2024

declared completion

22months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51800007183
Registered on17 Aug 2017
Promoter-declared completion31 Dec 2024
Current statusCertificate Signed
Against todayabout 22 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for KAVYA ASHWAMEGH record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for KAVYA ASHWAMEGH in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+18.

BuildingWingsFloorsDeclared completion
KAVYA ASHWAMEGH CHSL A WING1G+18-
KAVYA ASHWAMEGH CHSL B WING1G+18-

Legal and disputes

What disputes are disclosed?

6 complaints are on the MahaRERA record for KAVYA ASHWAMEGH, with orders passed in 5 of them.

6complaints

5with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000004403607/04/2018Yogesh Maru vs Kavya Construction Companyorder passed
CC00600000050040310/05/2024Yogesh Maru vs Kavya Construction Companyorder passed
CC00600000010056417/08/2019Shah Investments vs Kavya Construction Companyorder passed
CC00600000019698913/05/2021Tejas Maniar vs Kavya Construction Companyorder passed
CC00600000040855920/12/2023Rajesh Vinodchandra Shah vs KAVYA CONSTRUCTION COMPANYorder passed
CC1250196016/06/2025Rahul Suresh Belwalkar vs Mr Nimish Manshuklal Vorapending / no order on file

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2022DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION FOR 12 MONTHS
30 Jun 202231 Dec 2024DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION FOR 24 MONTHS

Location, Land & Connectivity

Located at MUMBAI, MUMBAI, Mumbai City, Mumbai City, 400075. Per the filed land record, the plot is bounded to the north by Bldg no 17 abutting ground 2 existing Structure, to the south by Abutting 12 20 meter wide road FOS, to the east by Abutting 12 20 meter wide road FOS and to the west by Bldg no 14 abutting ground 2 existing Structure. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 4 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Powai / Hiranandani business park4 km
Bandra Kurla Complex (BKC)5 km
Chhatrapati Shivaji Int'l Airport6 km
Andheri MIDC / SEEPZ7 km
Lower Parel / Worli business district13 km
Nariman Point / Fort20 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Ghatkopar East

Damji Shamji Corporate Square - Wing C
declared completion Dec 2026 · Coronate Constructions
Ashirwad CHS LTD
declared completion Dec 2026 · Shreedham Developers
Drushti Emerald
declared completion Dec 2026 · Samarth Drushti Developers
OM Makarand Heights
declared completion Dec 2026 · D D Infra
Shree Kalptaru CHS LTD
declared completion Dec 2026 · Conarch Lifespace LLP
Shree Suryodaya
declared completion Dec 2026 · Hariyana Developers
More projects in Mumbai Suburban

Other RERA-registered projects in Mumbai Suburban

Kavya KCD Prestine
declared completion Sep 2028 · Kavya KCD Buildcon LLP
KCD Aura
declared completion Dec 2024 · Town KCD Developers LLP
KCD Jogesh Eva
declared completion Dec 2025 · KCD Heritage Private Limited
KCD Lumin
declared completion Dec 2024 · KCD Heritage Private Limited
KCD Ridgewood
declared completion Sep 2023 · KCD Heritage PVT LTD
Kedar Darshan
declared completion Apr 2027 · Kosmos Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.