KCD RIDGEWOOD

BORIVALI · KCD HERITAGE PVT LTD

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Sep 2023declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for KCD RIDGEWOOD

MahaRERA · P51800009623

Delivery and registration

When is the project declared for completion?

KCD RIDGEWOOD is registered with MahaRERA as P51800009623 and the promoter has declared completion for 30 Sep 2023.

30 Sep 2023

declared completion

37months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51800009623
Registered on22 Aug 2017
Promoter-declared completion30 Sep 2023
Current statusCertificate Signed
Against todayabout 37 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for KCD RIDGEWOOD record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for KCD RIDGEWOOD in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+17.

BuildingWingsFloorsDeclared completion
KCD RIDGEWOOD1G+1731 Aug 2020

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for KCD RIDGEWOOD, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000037487021/03/2023Umesh Mohanlal Gohil vs KCD Heritage Private Limitedorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered28 Feb 2022DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED IN TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION.
28 Feb 202231 Mar 2023DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED IN TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 31/03/2023
31 Mar 202330 Sep 2023DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION STILL 30/09/2023

Location, Land & Connectivity

Located at BORIVALI, BORIVALI, Borivali, Mumbai Suburban, 400092. Per the filed land record, the plot is bounded to the north by BY PARTY PLOT OF PARWANA APARTMENTS, to the south by BY RAM NAGAR ROAD, to the east by PLOT P-1 and to the west by BY ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 10 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Andheri MIDC / SEEPZ10 km
Powai / Hiranandani business park13 km
Chhatrapati Shivaji Int'l Airport14 km
Bandra Kurla Complex (BKC)17 km
Lower Parel / Worli business district25 km
Nariman Point / Fort33 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Borivali West

Navkar Palazzo
Not filing quarterly progress reports · declared completion Dec 2026 · Navkar Infra Projects
THE Zone
declared completion Dec 2026 · MS Amann RAJ Housing AND Development Cor
9 Rajgir
declared completion Dec 2026 · M S Kavita Construction Company
Adarsh Garden Grove
declared completion Dec 2026 · Adarsh Enterprises
Akshaya AND Jayshree Redevelopment
declared completion Dec 2026 · NHI Developers LLP
Atulya
declared completion Dec 2026 · Phoenix Developers
More builders in Borivali West

Major developers building in Borivali West

More projects in Mumbai Suburban

Other RERA-registered projects in Mumbai Suburban

Kedar Darshan
declared completion Apr 2027 · Kosmos Developers
Kedarnath
declared completion Dec 2028 · Neeshiv Properties
Kedarnath Apartments
declared completion Dec 2027 · Majestic Royale Developers
Kenorita Jewels Phase II
declared completion Dec 2027 · K R Shoppers Private Limited
Kesar Leor
declared completion Aug 2026 · M S Realtors
Keshav Niwas
declared completion Oct 2023 · Bholanath Kapildev Gupta

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.