Developer RERA record

Lodha

Lodha has 258 RERA-registered projects: 186 projects under construction, Bengaluru averaging 11% construction; 71 projects past their declared completion date — a significant track-record flag. All figures are the developer's own regulator filings.

Mixed record
Delivery signal
186
Under construction
71
Past declared date
71%
Bengaluru inventory booked
220
RERA complaints filed

Under construction

Under construction — 186 projects

Construction % is the developer's own latest quarterly filing (Bengaluru, Gurgaon, Noida); MahaRERA files no construction %, so its projects show the declared possession date.

ProjectCityProgress / possession
AzurBengaluru20%
Azur Tower DBengaluru18%
Azur Phase 2Bengaluru7%
HavenBengaluru4%
Haven Phase 2Bengaluru4%
Acenza Tower A And BMumbaipossession by May 2027
Acenza Tower CMumbaipossession by Dec 2027
Acenza-Tower DMumbaipossession by Dec 2029
Adelphi A And BMumbaipossession by Mar 2031
Alibaug PlotsMumbaipossession by Aug 2029
Alibaug ProjectMumbaipossession by Mar 2030
Alibaug Residential ProjectMumbaipossession by Dec 2030
Alibaug TownhousesMumbaipossession by Aug 2029
AltusMumbaipossession by Dec 2030
Bellevue Tower - 3Mumbaipossession by Dec 2027
Bellissimo MatungaMumbaipossession by Dec 2027
Bellissimo Matunga -Tower 4 And Tower 5Mumbaipossession by Mar 2030
Bellissimo Matunga-Tower 2Mumbaipossession by Dec 2027
Bellissimo Matunga-Tower 3Mumbaipossession by Dec 2027
Bellissimo Mulund T2Mumbaipossession by Jun 2027
Belmondo Townhouse 4Punepossession by Aug 2030
Belvedere DMumbaipossession by Feb 2028
Belvedere EMumbaipossession by Sep 2029
Belvedere HMumbaipossession by May 2027
Belvedere IMumbaipossession by Jul 2028
Belvedere JMumbaipossession by Dec 2029
Belvedere-B And CMumbaipossession by Nov 2027
Belvedere-KMumbaipossession by Sep 2029
Bund Garden ProjectPunepossession by Apr 2028
Casa BelvedereMumbaipossession by Oct 2026
Corinthia -Tower 1 And Tower 2Mumbaipossession by May 2031
Corinthia Tower - 5Mumbaipossession by Nov 2031
Corinthia-Tower 6Mumbaipossession by Jun 2031
Crown Dombivli 1Mumbaipossession by Dec 2028
Crown Dombivli 2Mumbaipossession by Dec 2028
Crown Dombivli 3Mumbaipossession by Aug 2027
Crown Dombivli 4Mumbaipossession by Jun 2028
CullinanMumbaipossession by Dec 2028
Daffodil A And BMumbaipossession by Sep 2030
Daffodil C And DMumbaipossession by Sep 2029
Daffodil E And FMumbaipossession by Sep 2030
Daffodil G And HMumbaipossession by Sep 2030
Daffodil I And JMumbaipossession by Sep 2030
Daffodil K And LMumbaipossession by Sep 2030
Daffodil M And NMumbaipossession by Sep 2030
Dombivli ArcadeMumbaipossession by Oct 2027
Dreams Heights Building NO II C WingMumbaipossession by Mar 2029
Dreams Heights Building NO- IMumbaipossession by Sep 2026
Elanor - Tower 1Mumbaipossession by Dec 2031
Emerald A And BMumbaipossession by Aug 2028
Fiora G And HMumbaipossession by Oct 2026
Fiora IMumbaipossession by Feb 2030
Fiora JMumbaipossession by Jan 2029
Fiora KMumbaipossession by Jan 2028
Foresta EMumbaipossession by Aug 2028
Golf ViewMumbaipossession by Aug 2028
Hanging Garden PalavaMumbaipossession by Mar 2030
Hinjewadi Premium - Tower 10Punepossession by Jul 2032
Hinjewadi Premium - Tower 8Punepossession by Jan 2029
Hinjewadi Premium - Tower 9Punepossession by Jun 2031
Hinjewadi Premium-Tower 7Punepossession by Dec 2028
Hinjewadi ProjectPunepossession by Jun 2027
Hinjewadi Project-Tower 1Punepossession by Jun 2027
Hinjewadi Project-Tower 4 And 5Punepossession by Jun 2028
Hinjewadi Project-Tower 6Punepossession by Sep 2028
Hinjewadi Project-Tower APunepossession by Jun 2031
Hinjewadi Project-Tower BPunepossession by Jun 2031
Jardino AMumbaipossession by Aug 2027
Jardino BMumbaipossession by Aug 2028
Jasper C And DMumbaipossession by Aug 2028
Kharadi New Project - Tower 1Punepossession by Mar 2030
Kharadi NEW Project - Tower 3Punepossession by Mar 2030
Kharadi NEW Project -Tower 11Punepossession by Nov 2030
Kharadi New Project -Tower 2Punepossession by Mar 2030
Kharadi NEW Project -Tower 4Punepossession by Mar 2030
Kharadi NEW Project -Tower 5Punepossession by Sep 2030
Kharadi Pune P1Punepossession by Jun 2029
Kharadi Pune P2Punepossession by Oct 2027
Kharadi Pune P3Punepossession by May 2028
Kharadi Pune Phase I - Tower 1 To 4Punepossession by Oct 2026
Kharadi Pune Phase I -Tower 5Punepossession by May 2027
Kharadi Pune Phase II -Tower 6Punepossession by May 2027
Kharadi Pune Phase II Tower 7Punepossession by May 2027
Kharadi Pune Phase II Tower 8Punepossession by Jun 2029
Kharadi SignetPunepossession by Aug 2028
Kothrud Pune -Tower A And BPunepossession by Sep 2029
L-Square PrimePunepossession by Dec 2026
Liana CMumbaipossession by Sep 2026
Lily A And BMumbaipossession by Sep 2030
Lily C And DMumbaipossession by Sep 2030
Lily E And FMumbaipossession by Sep 2034
Lily G And HMumbaipossession by Sep 2030
Lily I And JMumbaipossession by Sep 2030
Lily K And LMumbaipossession by Sep 2035
Lodha Amara -Tower 42 And 43Mumbaipossession by Dec 2027
Lodha Amara Tower 24 And 25Mumbaipossession by Mar 2028
Lodha Amara Tower 44Mumbaipossession by Jun 2028
Lodha Amara Tower 47 And 48Mumbaipossession by Jun 2029
Lodha Amara Tower 49 And 50Mumbaipossession by Dec 2028
Lodha Bella Vita SignetPunepossession by Dec 2026
Lodha Bellagio-Tower CMumbaipossession by Dec 2026
Lodha Bellagio-Tower DMumbaipossession by Dec 2026
Lodha Bellavista - Wing B1Mumbaipossession by Jul 2028
Lodha Bellavista - Wing B2Mumbaipossession by Jul 2028
Lodha BellevueMumbaipossession by Sep 2028
Lodha Belmondo - Tower 30Punepossession by Dec 2026
Lodha Belmondo - Tower 32Punepossession by Oct 2028
Lodha Belmondo St. Andrews APunepossession by Feb 2027
Lodha Belmondo Townhouse 2Punepossession by Nov 2026
Lodha Crown Kolshet - Tower 2Mumbaipossession by Jul 2027
Lodha Crown Kolshet - Tower 3Mumbaipossession by Sep 2028
Lodha Crown Kolshet-Tower 1Mumbaipossession by Sep 2026
Lodha Eternis Idyllia AMumbaipossession by Jun 2027
Lodha Hinjewadi Phase 3Punepossession by Jun 2031
Lodha Kandivali Project-Tower 1Mumbaipossession by Feb 2028
Lodha Kolshet A2 - Tower 3Mumbaipossession by Sep 2031
Lodha Mahalakshmi - SignetMumbaipossession by Aug 2027
Lodha MalabarMumbaipossession by Jun 2027
Lodha MatungaMumbaipossession by Apr 2028
Lodha Miraroad Tower - 1 And Tower - 2Mumbaipossession by Mar 2027
Lodha Mulund Project Tower 1Mumbaipossession by Sep 2027
Lodha NCP Tower - 1Mumbaipossession by Dec 2026
Lodha NCP Tower - 2Mumbaipossession by Jun 2030
Lodha ProminaMumbaipossession by Dec 2031
Lodha Pune Nibm Project- Tower 7,8 And 9Punepossession by Dec 2027
Lodha Pune Nibm Project-Tower 10Punepossession by Dec 2026
Lodha Pune Nibm Project-Tower 5Punepossession by Dec 2026
Lodha Pune Nibm Project-Tower 6Punepossession by Dec 2026
Lodha Sewri ProjectMumbaipossession by Dec 2032
Lodha Signet B - KolshetMumbaipossession by Nov 2027
Lodha Sterling - Tower CMumbaipossession by Mar 2030
Lodha Vikhroli - Tower C1Mumbaipossession by Dec 2028
Lodha Vikhroli-SignetMumbaipossession by Jun 2028
Lodha Villa Royale Tdlr 2Mumbaipossession by Dec 2027
Lodha Woods - Tower 6Mumbaipossession by Nov 2027
Lodha Woods - Tower 7Mumbaipossession by Jul 2027
Lodha Woods- Tower 8Mumbaipossession by Nov 2028
Lodha Worli Residential ProjectMumbaipossession by Jun 2033
LVR Palava -Ready Villas On LandMumbaipossession by Mar 2028
MarqMumbaipossession by Nov 2028
Matunga SignetMumbaipossession by Sep 2029
Matunga Wing BMumbaipossession by Mar 2029
Olivia Tower - AMumbaipossession by Jun 2027
Olivia Tower -BMumbaipossession by Mar 2027
Opulis AMumbaipossession by Nov 2030
Opulis BMumbaipossession by Nov 2030
Opulis CMumbaipossession by Nov 2030
Opulis DMumbaipossession by Nov 2030
Opulis EMumbaipossession by Apr 2031
Opulis FMumbaipossession by Dec 2031
Palava -Signet 2Mumbaipossession by Jul 2027
Palava MagnoliaMumbaipossession by Dec 2029
PearlMumbaipossession by Mar 2028
Pune Wakad ProjectPunepossession by Jun 2031
Sea FaceMumbaipossession by Feb 2029
Sovrano Tower CMumbaipossession by Dec 2030
Sovrano Tower-AMumbaipossession by Mar 2031
Sovrano Tower-BMumbaipossession by Dec 2030
Stella-Tower BMumbaipossession by Dec 2030
Thane ProjectMumbaipossession by Jul 2029
The Baya SanctumMumbaipossession by Jun 2028
TulipMumbaipossession by May 2027
Upper Thane - Eden DMumbaipossession by Mar 2028
Upper Thane - Eden EMumbaipossession by May 2027
Upper Thane - Tiara GMumbaipossession by Jan 2028
Upper Thane - Woodlands A, B AND JMumbaipossession by Oct 2026
Upper Thane-Casa EdenMumbaipossession by Sep 2026
Upper Thane-Iris Wing AMumbaipossession by Dec 2027
Upper Thane-Iris Wing BMumbaipossession by Mar 2028
Upper Thane-Iris Wing CMumbaipossession by Dec 2026
Upper Thane-Iris Wing DMumbaipossession by Oct 2027
Upper Thane-Iris Wing GMumbaipossession by May 2028
Upper Thane-Mlcp C ShopsMumbaipossession by Dec 2026
Upper Thane-SupremusMumbaipossession by May 2028
Upper Thane-Tiara HMumbaipossession by Jul 2027
Upper Thane-Verdura AMumbaipossession by Jul 2028
Upper Thane-Woodlands BMumbaipossession by Mar 2028
Vikhroli Aspi Project 1Mumbaipossession by Sep 2029
Vikhroli Aspi Project 2Mumbaipossession by Jan 2029
Vikhroli Aspi Project 3Mumbaipossession by Sep 2029
Vikhroli Aspi Project 4Mumbaipossession by Dec 2030
Vikhroli Premium Tower A1Mumbaipossession by Dec 2030
Vikhroli Tower C3Mumbaipossession by Dec 2029
Villa ImperioMumbaipossession by Dec 2030
WaterviewMumbaipossession by Jun 2028
Woods Tower 9Mumbaipossession by Dec 2029
Considering a specific Lodha project? Tell us which one and we'll send you its full RERA record — completion certificate, construction history, quarterly updates.
Past declared date (71)click to expand

The declared completion date has passed with no completion certificate on record. Many projects receive RERA extensions, and MahaRERA publishes no OC at all — so this is the raw disclosure, not a verdict on delivery. Verify current status on the RERA portal.

ProjectCityDeclared date
Casa Royale - GrandeMumbai2018-07
Casa Selva A To CMumbai2025-03
Codename One And OnlyMumbai2026-06
Crown Splendora - Tower 1Mumbai2025-11
Dreams Heights Building NO IIMumbai2025-09
Fiora A, B And CMumbai2025-11
Fiora DMumbai2026-01
Fiora EMumbai2026-03
Fiora FMumbai2026-08
Foresta & FioraMumbai2023-08
L SquarePune2022-12
Liana DMumbai2026-08
Lodha AdrinaMumbai2026-06
Lodha Amara - Tower 1 - 5, 7 - 19Mumbai2019-11
Lodha Amara - Tower 23Mumbai2022-12
Lodha Amara - Tower 29,31Mumbai2022-07
Lodha Amara - Tower 32,33Mumbai2022-08
Lodha Amara - Tower 6, 22Mumbai2024-01
Lodha Amara - Wing 40 And 41Mumbai2025-11
Lodha Amara Mlcp RetailMumbai2022-07
Lodha Belmondo - Estancia BPune2018-08
Lodha Belmondo - Pebble Beach DPune2018-12
Lodha Belmondo Ashbridge D, EPune2017-12
Lodha Belmondo Augusta CPune2017-12
Lodha Belmondo St. Andrews B,c,d Villa 1 To 28Pune2018-07
Lodha Belmondo ST. Andrews EPune2019-12
Lodha Belmondo Townhouse 3Pune2026-03
Lodha Crown Kolshet-Tower 4Mumbai2026-05
Lodha Eternis Serena AMumbai2019-12
Lodha FiorenzaMumbai2018-01
Lodha Kandivali Project - Tower 2Mumbai2025-12
Lodha Kandivali Project - Tower 2Mumbai2026-07
Lodha Kandivali Project - Tower 3Mumbai2026-06
Lodha Kandivali Project - Tower 4Mumbai2025-05
Lodha Kandivali Project - Tower 5Mumbai2026-07
Lodha Majiwada - Tower 4Mumbai2022-11
Lodha Majiwada - Tower 5Mumbai2022-11
Lodha Panacea IIMumbai2025-03
Lodha Panacea IIIMumbai2026-06
Lodha Parel ProjectMumbai2023-10
Lodha Pune Nibm ProjectPune2026-07
Lodha Quality Home Tower - 5Mumbai2025-03
Lodha Quality Home Tower 1Mumbai2024-07
Lodha Quality Home Tower 2Mumbai2024-07
Lodha Quality Home Tower 3Mumbai2024-09
Lodha Quality Home Tower 4Mumbai2024-09
Lodha Quality Home Tower 6Mumbai2025-09
Lodha Quality Home Tower 7Mumbai2026-03
Lodha Signet Lower Parel Wing BMumbai2026-08
Lodha Splendora - Platino - BMumbai2019-03
Lodha Splendora - Platino - DMumbai2022-09
Lodha Sterling - Tower GMumbai2025-09
Lodha Supremus - Thane, KolshetMumbai2022-07
Lodha Villa Royale PalavaMumbai2025-09
NCP Commercial Tower - SupremusMumbai2024-03
NCP Commercial Tower 1 - Floors 24 To 28Mumbai2019-06
NEW Cuffe Parade - Lodha EnchanteMumbai2019-06
New Cuffe Parade - Lodha GardeniaMumbai2023-03
NEW Cuffe Parade -Lodha AltiaMumbai2022-03
Palava Olivia AMumbai2025-11
Palava Serenity BMumbai2025-07
Palava Serenity CMumbai2025-03
Palava Urbano D AND EMumbai2022-10
Regalia ShopsMumbai2020-07
Upper Thane - Meadows AMumbai2025-09
Upper Thane - Meadows E, F, GMumbai2025-10
Upper Thane - Tiara HMumbai2025-11
Upper Thane - Woodlands C AND DMumbai2025-12
Upper Thane - Woodlands G,h,iMumbai2023-09
Urbano 2 ShopsMumbai2020-07
Violet G, H And IMumbai2026-04
Registered, no progress filed yet (1)click to expand
ProjectCity
Fiorana@Beaumont Estate(Phase-1)Bengaluru

RERA complaints & orders

Regulatory record

220 total complaints filed — among the highest complaint volumes of any builder we track (#2 of 62).

219
MahaRERA complaints
1
Karnataka RERA complaints

Complaint counts and order records are sourced directly from RERA portals. A complaint is a filing by a buyer or association; an order is a formal ruling. Not all complaints lead to adverse orders. This is regulatory disclosure, not a verdict.

Figures are Lodha's own disclosures on RERA registers, grouped to the consumer-facing developer brand. "Completed" means an OC is on the project's RERA record; construction % is the developer's latest quarterly filing. Past-deadline projects may have received extensions — always verify on the relevant RERA portal. See our market reports for context.