Mumbai/Project record

MahaRERA · the public record

Keshav Niwas

Mulund · BHOLANATH KAPILDEV GUPTA

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
31 Oct 2023declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for Keshav Niwas

MahaRERA · P51800009449

Delivery and registration

When is the project declared for completion?

Keshav Niwas is registered with MahaRERA as P51800009449 and the promoter has declared completion for 31 Oct 2023.

31 Oct 2023

declared completion

36months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51800009449
Registered on22 Aug 2017
Promoter-declared completion31 Oct 2023
Current statusCertificate Signed
Against todayabout 36 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Keshav Niwas record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Keshav Niwas in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+9.

BuildingWingsFloorsDeclared completion
KESHAV NIWAS1G+930 Oct 2021

Legal and disputes

What disputes are disclosed?

5 complaints are on the MahaRERA record for Keshav Niwas, with orders passed in 5 of them.

5complaints

5with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000005694116/11/2018Mudra Abhijeet Chavre vs B N Guptaorder passed
CC00600000019420101/10/2020TARACHAND PREMJI DEDHIA vs M/S DHANALAXMI BUILDERS & DEVELOPERSorder passed
CC00600000019423301/10/2020AJIT D WADEKAR, SUMAN A WADEKAR vs M/S DHANALAXMI BUILDERS & DEVELOPERSorder passed
CC00600000019425211/10/2020MRS. UJWALA SOPAN KOLTE, MR. SOPAN KOLTE vs M/S DHANALAXMI BUILDERS & DEVELOPERSorder passed
CC00600000019715304/06/2021VIJAY NARAYAN BHOSLE vs M/S. DHANALAXMI BUILDERS & DEVELOPERSorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered30 May 2020To, The Concerned Officer, Maharashtra Real Estate Regulatory Authority (MahaRERA) Bandra, Mumbai Subject – Self Declaration for extension of due date for the project registere
30 May 202030 Apr 2021I Mr. Bholanath Kapildev Gupta, Proprietor do hereby declare that the project “Keshav Niwas” is registered with MahaRERA vide Registration Number “P51800009449” and end date for th
30 Apr 202131 Oct 2023AS PER ATTACHMENT

Location, Land & Connectivity

Located at Mulund, Mulund, Kurla, Mumbai Suburban, 400081. Per the filed land record, the plot is bounded to the north by 19 10 13 N 72 57 38 E, to the south by 19 12 10 N 72 57 38 E, to the east by 72 57 39 E and to the west by 72 57 38 W. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 8 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Powai / Hiranandani business park8 km
Andheri MIDC / SEEPZ11 km
Chhatrapati Shivaji Int'l Airport13 km
Bandra Kurla Complex (BKC)15 km
Lower Parel / Worli business district23 km
Nariman Point / Fort31 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Mulund East

Mithagar Road Ekta Chsl
declared completion Dec 2026 · Palan Realty Private Limited
Bimal Apartment Chsl
declared completion Dec 2026 · Rite Builders & Developers
Govind Prakash SRA CHS LTD
declared completion Dec 2026 · Omsai Developers
Jvms Monica Gardens
declared completion Dec 2026 · JVM Spaces
Mahatma Jyotiba Phule CHS LTD
declared completion Dec 2026 · Tridevh Construction Company
OM Mayuresh
declared completion Dec 2026 · M/s Keytech
More builders in Mulund East

Major developers building in Mulund East

More projects in Mumbai Suburban

Other RERA-registered projects in Mumbai Suburban

Keshav Shiv Heights
declared completion Dec 2018 · Inventure Sejal Realtors Pvt. Ltd.
Keshavpada
declared completion Dec 2025 · Namah Realtor
Keva
declared completion Nov 2027 · Pinal Realty LLP
Kevli Plaza – A Wing AND Kevli Darshan – B Wing
declared completion Dec 2028 · M/s R K AND Company PVT LTD
KEY Tech Park
declared completion Dec 2026 · M/s Keytech
Khadija Hitech Tower
declared completion Dec 2021 · Hitech Hafizi Town Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.