Developer RERA record

Shriram Properties

Shriram Properties has 56 RERA-registered projects: 20 projects under construction, Bengaluru averaging 52% construction; 27 projects past their declared completion date. All figures are the developer's own regulator filings.

20
Under construction
1
Completed / delivered
27
Past declared date
100%
Bengaluru inventory booked
29
RERA complaints filed

Public registration records

These records have not been classified as delivered, under construction or overdue. The declared date and status are filings, not a current site inspection.

Shriram Santrupthi - Phase 2

Chennai region · Registered: 2026-05-14 · Declared completion: 2028-02-05 · Filed status: Change of Project Bank: SBM Bank (India) Limited, Mylapore Branch, Chennai - 600004 (Collection account details omitted, Separate account details omitted, Transaction account details omitted)

SHRIRAM SWARGAM

Chennai region · Registered: 2026-06-30 · Declared completion: 2029-12-14

SHRIRAM STELLAR

Chennai region · Registered: 2026-06-04 · Declared completion: 2032-10-22

YASHOVIHHAR-TS

Hyderabad region · Registered: 2020-03-20 · Declared completion: 2021-07-31

Under construction

Under construction — 20 projects

Construction % is the developer's own latest quarterly filing (Bengaluru, Gurgaon, Noida); MahaRERA files no construction %, so its projects show the declared possession date.

Bengaluru: 1.0/5 ★☆☆☆☆ (1 MouthShut reviews)

ProjectCityProgress / possession
SHRIRAM ESQUIREBengaluru74%
SHRIRAM SAPPHIREBengaluru56%
SHRIRAM SERENITYBengaluru20%
SHRIRAM SONGS OF THE EARTHBengaluru12%
Anand SagarNagpurpossession by Dec 2026
Bajrang Complex Wing APunepossession by Jun 2027
Divine Garden Phase 1Punepossession by Dec 2026
Divine Garden Phase IIPunepossession by Dec 2026
OM SAI Metro ParkNagpurpossession by Dec 2029
Shriram Corner Phase 2Punepossession by Dec 2026
Shriram ElitePunepossession by Dec 2030
Shriram NiwasMumbaipossession by Jun 2027
Shriram NyraPunepossession by Dec 2029
Shriram Park Magic TowerPunepossession by Dec 2026
Shriram TowerMumbaipossession by Dec 2029
Shriram VandanPunepossession by Dec 2030
Shriram VishwaPunepossession by Dec 2027
THE SpectrumPunepossession by Apr 2035
Unity ParkPunepossession by Dec 2026
Vivaan ParkPunepossession by Dec 2026
Considering a specific Shriram Properties project? Tell us which one and we'll send you its full RERA record — completion certificate, construction history, quarterly updates.
Delivered projects (1)click to expand
ProjectCityStatus
SHRIRAM HEBBAL 1Bengaluru100% built
Past declared date (27)click to expand

The declared completion date has passed with no completion certificate on record. Many projects receive RERA extensions, and MahaRERA publishes no OC at all — so this is the raw disclosure, not a verdict on delivery. Verify current status on the RERA portal.

ProjectCityDeclared date
SHRIRAM SUMMITTBengaluru2019-12
SHRIRAM SAMEEKSHABengaluru2018-09
SHRIRAM HEBBAL ONEBengaluru2022-04
Highfield ParkPune2019-06
Highfield Park Phase IIPune2023-12
Kanhaiya MajestyPune2021-12
Mahalaxmi PlazaNagpur2025-01
Nature ParkPune2025-12
Nature ParkPune2025-12
Nature ParkPune2025-12
Nature ParkPune2025-12
SAI Shanti ParkPune2019-06
SAI Shanti ParkPune2023-12
Shreeyansh ParkPune2026-06
Shriram CornerPune2022-12
Shriram KrupaPune2025-03
Shriram NagariNagpur2025-05
Shriram Niwas Yojna - IiNagpur2017-12
Shriram Plaza IINagpur2020-12
Shriram PridePune2021-12
Shriram Pride BuildingPune2021-12
Shriram ResidencyNagpur2023-12
Shriram SahaniwasNagpur2020-12
Shriram TowerNagpur2019-12
ShriramcityPune2025-12
T JunctionPune2021-12
Varad ResidencyPune2022-05

RERA complaints & orders

Regulatory record

29 total complaints filed — above average for builders we track (77th percentile).

28
MahaRERA complaints
1
Karnataka RERA complaints

Complaint counts and order records are sourced directly from RERA portals. A complaint is a filing by a buyer or association; an order is a formal ruling. Not all complaints lead to adverse orders. This is regulatory disclosure, not a verdict.

Figures are Shriram Properties's own disclosures on RERA registers, grouped to the consumer-facing developer brand. "Completed" means an OC is on the project's RERA record; construction % is the developer's latest quarterly filing. Past-deadline projects may have received extensions — always verify on the relevant RERA portal. See our market reports for context.