Pune/Project record

MahaRERA · the public record

SAI SHANTI PARK

Pune · SHRIRAM REALITY

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Jun 2019declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for SAI SHANTI PARK

MahaRERA · P52100001544

Delivery and registration

When is the project declared for completion?

SAI SHANTI PARK is registered with MahaRERA as P52100001544 and the promoter has declared completion for 30 Jun 2019.

30 Jun 2019

declared completion

88months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP52100001544
Registered on28 Jul 2017
Promoter-declared completion30 Jun 2019
Current statusCertificate Signed
Against todayabout 88 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SAI SHANTI PARK record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Promoter record

What else is this promoter on record for?

SHRIRAM REALITY is the promoter of record on 3 projects registered with MahaRERA.

3projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SAI SHANTI PARK in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+9.

BuildingWingsFloorsDeclared completion
A WING1G+9-
B WING1G+9-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2019Dear sir, we would like to extend the project completion date upto 30-06-2019. Due to material shortage and overall slowdown in the booking of the flats, the scheme is getting dela

Location, Land & Connectivity

Located at Haveli, Pune, 411047. Per the filed land record, the plot is bounded to the north by PLOT BEARING 284-4, to the south by 283, to the east by PORWAL ROAD and to the west by PLOT BEARING 284-5-1. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 7 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Pune Int'l Airport (Lohegaon)3 km
Kharadi / EON IT Park7 km
Pune Junction / city centre9 km
Magarpatta / Hadapsar IT10 km
Baner–Balewadi belt15 km
Hinjewadi Rajiv Gandhi IT Park18 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

See every Shriram Reality project & its RERA track record →

Other RERA-registered projects in Lohgaon

Youthika
declared completion Oct 2026 · Krushnarang Group
Pankaj Aasmaan Phase V
declared completion Dec 2026 · Pankaj Developers
Aayush Wisteria
declared completion Dec 2026 · Pritam Kantilal Khandve
Divine Garden Phase 1
declared completion Dec 2026 · Shriram Associates
Divine Garden Phase II
declared completion Dec 2026 · Shriram Associates
Goodwill Metropolis East Phase 2
declared completion Dec 2026 · Krishna Buildcon
More builders in Lohgaon

Major developers building in Lohgaon

More projects in Pune

Other RERA-registered projects in Pune

SAI Shanti Park
declared completion Dec 2023 · Shriram Realty
Sai Shawas
declared completion Dec 2026 · Vilas Tukaram Wadghule
Sai Shilp Kukade Parisar
declared completion Dec 2023 · The Nest Constructions
SAI Shraddha Park PH II Wing M N O P Project
declared completion Dec 2023 · Gauri Space Creator
SAI Shraddha Trade Centre
declared completion Dec 2023 · Shree Saishraddha Developers & Build
SAI Shreeman
declared completion Dec 2027 · SAI RJ Constructions

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Pune projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.