Mumbai/Project record

MahaRERA · the public record

MAGNUM HOMES

ACHOLE ROAD · MAGNUM DEVELOPERS

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
31 Dec 2025declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for MAGNUM HOMES

MahaRERA · P99000018289

Delivery and registration

When is the project declared for completion?

MAGNUM HOMES is registered with MahaRERA as P99000018289 and the promoter has declared completion for 31 Dec 2025.

31 Dec 2025

declared completion

10months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP99000018289
Registered on22 Oct 2018
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 10 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for MAGNUM HOMES record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (2025-06-30).

Promoter record

What else is this promoter on record for?

MAGNUM DEVELOPERS is the promoter of record on 3 projects registered with MahaRERA.

3projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for MAGNUM HOMES in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
LAXMI DURGA COMPLEX1G+831 Dec 2021
LAXMI DURGA1-31 Dec 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2023Dear Sir, With reference to cited subject, I the undersigned developer of the Project MAGNUM HOMES would like to inform you that my Maharera Project due date has been expired, Due
30 Dec 202331 Dec 2025DEAR SIR, DUE TO POST COVID 19 MARKET SLOW DOWN AND NON RECOVERY OF RECEIPT FROM ALLOTEES, PROJECT DEVLOPMENT HAS BEEN DELAYED. AND THEREFORE, WE SEEK FURTHER EXTENSION TILL 31-12

Location, Land & Connectivity

Located at ACHOLE ROAD, SANKESHWAR NAGAR , Vasai, Palghar, 401209. Per the filed land record, the plot is bounded to the north by BLDG NO 3, to the south by BLDG NO 5, to the east by 40 M DP ROAD and to the west by BLDG NO 7. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Nallasopara East

N G Platinum City
declared completion Dec 2026 · J M G Realtors PVT LTD
Rudra Heights Bldg NO 1 Wing -G
declared completion Dec 2026 · Aura Navkar Developers
Ajay CO-Operative Housing Society LTD
declared completion Dec 2026 · MAA Guru Construction
Imperialparamount
declared completion Dec 2026 · Shivganga Construction & Redeveloper
Precilla CHS LTD
declared completion Dec 2026 · Blue OAK Infrastructure
Samaira Residency
declared completion Dec 2026 · AV Crystal Space
More projects in Palghar

Other RERA-registered projects in Palghar

Mahadev Complex
declared completion Dec 2030 · Ossho Builders AND Developers
Mahalaxmi Dham
declared completion Oct 2023 · Sangeeta Sunil Singh
Mahalaxmi Heights
declared completion Dec 2028 · Not Available
Mahalaxmi Nagar - Bldg No.5
declared completion Dec 2028 · Mahalaxmi Homemakers Private Limited
Mahalaxmi Nagar Building NO 4
declared completion Jul 2031 · Mahalaxmi Homemakers Private Limited
Mahalaxmi Residency
declared completion Dec 2022 · Arpita Realtors AND Infra Private Limite

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 11 Sep 2026. Document and inventory dates are shown in their sections.