Mumbai/Project record

MahaRERA · the public record

METROPOLIS

TALOJA · METRO INFRA

Is this the right project?
Which unit should you choose?

Read the free RERA facts below. For help choosing a unit or comparing a price, select a report.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Dec 2023declared completionMahaRERA registration · read 19 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 19 Jul 2026

Free project details

Registration read 19 Jul 2026

RERA details for METROPOLIS

MahaRERA · P52000022444

Delivery and registration

When is the project declared for completion?

METROPOLIS is registered with MahaRERA as P52000022444 and the promoter has declared completion for 30 Dec 2023.

30 Dec 2023

declared completion

34months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 19 Jul 2026

MahaRERA registrationP52000022444
Registered on24 Sep 2019
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 34 months past the declared date

Promoter record

What else is this promoter on record for?

METRO INFRA is the promoter of record on 2 projects registered with MahaRERA.

2projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 19 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for METROPOLIS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 19 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
METROPOLIS1G+831 Dec 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2023Due to covid,unavailabilty of material and labour.

Location, Land & Connectivity

Located at TALOJA, PLOT NO 20 SECTOR-16, Panvel, Raigarh, 410206. Per the filed land record, the plot is bounded to the north by 15 M WIDE ROAD, to the south by PLOT NO 21, to the east by 11 M WIDE ROAD and to the west by PLOT NO 19. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Panvel

Shreeji Icon
declared completion Oct 2026 · Shreeji Lifespaces Group
Govind Ameya
declared completion Oct 2026 · Mansarovar Constructions
Shikara Greens Phase I
declared completion Oct 2026 · Shikara Constructions Pvt. Ltd.
Ambers Dnyaneshwar Capital
declared completion Nov 2026 · Capital Builders
Govind Greens
declared completion Nov 2026 · Priyal Buildcon LLP
Jupiter Royal
declared completion Nov 2026 · Arjun Ashok Tarachandani
More builders in Panvel

Major developers building in Panvel

More projects in Raigarh

Other RERA-registered projects in Raigarh

Metrosatyam Grand Atlantis
declared completion Mar 2031 · Metrosatyam Luxury Homes LLP
MG Landmarks
declared completion Dec 2027 · M.g. Landmarks Private Limited
Micron Residency
declared completion Jul 2026 · Micron Infra
Milestone Corner
declared completion Jun 2024 · Neelkanth Infra
Millenium Height
declared completion Dec 2022 · Millennium Group
Millenium Infinia
declared completion Jun 2026 · Millenium Skyline Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.