Mumbai/Project record

MahaRERA · the public record

N G CANARY PHASE II

Ghodbunder · RNA Builders (NG)

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
29 Jun 2022declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for N G CANARY PHASE II

MahaRERA · P51700018931

Delivery and registration

When is the project declared for completion?

N G CANARY PHASE II is registered with MahaRERA as P51700018931 and the promoter has declared completion for 29 Jun 2022.

29 Jun 2022

declared completion

52months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51700018931
Registered on17 Dec 2018
Promoter-declared completion29 Jun 2022
Current statusCertificate Signed
Against todayabout 52 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for N G CANARY PHASE II record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Promoter record

What else is this promoter on record for?

RNA Builders (NG) is the promoter of record on 24 projects registered with MahaRERA.

24projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for N G CANARY PHASE II in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+9.

BuildingWingsFloorsDeclared completion
N G CANARY C1G+930 Jun 2020
N G CANARY D1G+930 Jun 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered29 Dec 2021We RNA Builders had registered our project N G Canary Phase 2 vide project registration number P51700018931 On 17/12/2018. Due to Covid 19 Pandemic our project cycle was disturbed

Location, Land & Connectivity

Located at Ghodbunder, Ghodbunder, Mumbai City, Mumbai City, 401104. Per the filed land record, the plot is bounded to the north by RAJ REALTY HSG SOCIETY, to the south by MUNICIPAL D P ROAD, to the east by MUNICIPAL NALA N G PARADISE and to the west by HATKESH ROAD. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

See every RNA Builders project & its RERA track record →

Other RERA-registered projects in Kashimira

SAI Enclave Wing B
declared completion Dec 2026 · Mehta Realty
Meera Queen
declared completion Dec 2028 · Not Available
Forest Vista
declared completion Dec 2036 · Kashimira Ceramic Products LLP
Ruheena Appartment
Past its declared completion date · declared completion Dec 2022 · Sairajdevelop
Hiraco Eminence Phase 2
declared completion Sep 2020 · Kashimira Ceramic Products LLP
ANA Avant Garde Phase 1
declared completion Dec 2019 · Steelfab Engineering Corporation
More projects in Thane

Other RERA-registered projects in Thane

N G Diamond Hill A Phase III
declared completion Dec 2024 · RNA Builders
N G Diamond Hill B Phase I
declared completion Dec 2021 · RNA Builders
N G Diamond Hill C Phase IV
declared completion Dec 2024 · RNA Builders
N G Diamond Hill D Phase II
declared completion Dec 2022 · RNA Builders
N G Grand Empire Phase I
declared completion Dec 2026 · RNA Builders
N G Grand Empire Phase II
declared completion Dec 2028 · RNA Builders

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.