Mumbai/Project record

MahaRERA · the public record

Omkar Prarthana

Mumbai Suburban · Prarthana Constructions

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
31 Jan 2021declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for Omkar Prarthana

MahaRERA · P51800008170

Delivery and registration

When is the project declared for completion?

Omkar Prarthana is registered with MahaRERA as P51800008170 and the promoter has declared completion for 31 Jan 2021.

31 Jan 2021

declared completion

69months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51800008170
Registered on18 Aug 2017
Promoter-declared completion31 Jan 2021
Current statusCertificate Signed
Against todayabout 69 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Omkar Prarthana record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Promoter record

What else is this promoter on record for?

Prarthana Constructions is the promoter of record on 3 projects registered with MahaRERA.

3projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Omkar Prarthana in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11.

BuildingWingsFloorsDeclared completion
Omkar Prarthana CHS1G+8-
Prarthana Star1G+11-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 3 court cases on this project to MahaRERA. Filed descriptions (status fields empty): 3 “Pending”. These are the promoter's filed statements, not a current court check. A disposed application or motion does not establish that the whole case is closed. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your unit. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Mumbai City Civil Court15192012Status not supplied
Filed description: Pending
Mumbai Cmm Court1762009Status not supplied
Filed description: Pending
Mumbai Cmm CourtSW/1662014Status not supplied
Filed description: Pending

Location, Land & Connectivity

Located at Andheri, Mumbai Suburban, 400069. Per the filed land record, the plot is bounded to the north by Sambhaji Nagar, to the south by Kalpita Enclave CHS, to the east by Swami Nityanand Marg and to the west by Sambhaji Nagar. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 1 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Andheri MIDC / SEEPZ1 km
Chhatrapati Shivaji Int'l Airport3 km
Powai / Hiranandani business park3 km
Bandra Kurla Complex (BKC)6 km
Lower Parel / Worli business district14 km
Nariman Point / Fort22 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Andheri East

Amey Apartments
declared completion Oct 2026 · Amey Realty AND Construction LLP
Elegant Residency
declared completion Dec 2026 · Elegant Builders AND Developers
Girnar Residency Wing B Phase 1
declared completion Dec 2026 · Nidhaan Realty LLP
HEM Ratan Apartments AND Kamlesh Apartments
declared completion Dec 2026 · NEW India Construction Company
Jyoti Skyline
declared completion Dec 2026 · Jyoti Shelter
Nicco Residency
declared completion Dec 2026 · Neelkamal Realty & Construction LLP
More builders in Andheri East

Major developers building in Andheri East

More projects in Mumbai Suburban

Other RERA-registered projects in Mumbai Suburban

Omkar Sejal
declared completion Jun 2028 · Shraddha Divine Realtors LLP
Omkara Unchai
declared completion Mar 2027 · Omkara Infratech
Omnia Residences
declared completion Dec 2028 · Gold Fusion Realty Private Limited
ONE Alag
declared completion Dec 2028 · Alag Infraestate LLP
ONE Amaad
declared completion Jul 2025 · Amaad Developers
ONE Apollo
declared completion Dec 2025 · Goldnest Spaces LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.