PALAI COMMERCIAL COMPLEX

Senapati Bapat Marg · DHANJI GELABHAI GALA

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
31 May 2024declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for PALAI COMMERCIAL COMPLEX

MahaRERA · P51900011317

Delivery and registration

When is the project declared for completion?

PALAI COMMERCIAL COMPLEX is registered with MahaRERA as P51900011317 and the promoter has declared completion for 31 May 2024.

31 May 2024

declared completion

29months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51900011317
Registered on31 Aug 2017
Promoter-declared completion31 May 2024
Current statusCertificate Signed
Against todayabout 29 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for PALAI COMMERCIAL COMPLEX record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Promoter record

What else is this promoter on record for?

DHANJI GELABHAI GALA is the promoter of record on 3 projects registered with MahaRERA.

3projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for PALAI COMMERCIAL COMPLEX in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+10.

BuildingWingsFloorsDeclared completion
PALAI COMMERCIAL COMPLEX1G+1031 Jul 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered31 Jul 2020Dear Sir, With reference to the captioned subject, we would like to inform your goodself that our project ‘Palai Commercial Complex’is registered on the MahaRERA webportal vide R
31 Jul 202031 Dec 2022Dear Sir, With reference to the captioned subject, we would like to inform your goodself that our project ‘Palai Commercial Complex’ is registered on the MahaRERA webportal vid
31 Dec 202231 May 2024The Secretary, Maharashtra Real Estate Regulatory Authority 3rd Floor, A-Wing, Slum Rehabilitation Authority, Administrative Building, Anant Kanekar Marg, Bandra (E), Mumbai 40

Location, Land & Connectivity

Located at Senapati Bapat Marg , Dadar West , Mumbai City, Mumbai City, 400028. Per the filed land record, the plot is bounded to the north by V S MATKAR MARG, to the south by FINAL PLOT NO 555, to the east by SENAPATI BAPAT MARG and to the west by FINAL PLOT NO 544. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 2 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Lower Parel / Worli business district2 km
Bandra Kurla Complex (BKC)7 km
Chhatrapati Shivaji Int'l Airport9 km
Nariman Point / Fort10 km
Andheri MIDC / SEEPZ13 km
Powai / Hiranandani business park14 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dadar West

Sugee Sukrut
declared completion Oct 2026 · Sugee Nine Developers LLP
1891 Ekam Parkk
declared completion Dec 2026 · Nascent Developers
Cynthiandra
declared completion Dec 2026 · Shubh Laxmi Developers
Shree SAI Arti
declared completion Dec 2026 · V.K Developers
Sigma Garnet
declared completion Dec 2026 · Colo Color Private Limited
Amara
declared completion Dec 2026 · Sharcon Mutha
More builders in Dadar West

Major developers building in Dadar West

More projects in Mumbai City

Other RERA-registered projects in Mumbai City

Palazzo
declared completion Dec 2026 · Livstone Estates LLP
Palette
declared completion Sep 2026 · Suraj Estate Developers LTD
Panchratna-NX
declared completion Dec 2026 · Sudhir Kishor Desai
Pantnagar Swapnalok CHS Ltd
declared completion Jun 2023 · Chetana Enterprises - NX
Paramount
declared completion Feb 2030 · Gala Habitats LLP
Parasmani - B
declared completion May 2025 · Parasmani Constructions Pvt .ltd

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.