Mumbai/Project record

MahaRERA · the public record

PARDESHI EMPIRE

TITWALA · VISHNU DEVELOPERS

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
31 Mar 2025declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for PARDESHI EMPIRE

MahaRERA · P51700034711

Delivery and registration

When is the project declared for completion?

PARDESHI EMPIRE is registered with MahaRERA as P51700034711 and the promoter has declared completion for 31 Mar 2025.

31 Mar 2025

declared completion

19months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51700034711
Registered on20 Apr 2022
Promoter-declared completion31 Mar 2025
Current statusCertificate Signed
Against todayabout 19 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for PARDESHI EMPIRE record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.

Promoter record

What else is this promoter on record for?

VISHNU DEVELOPERS is the promoter of record on 3 projects registered with MahaRERA.

3projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for PARDESHI EMPIRE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
PARDESHI EMPIRE1G+631 Mar 2024

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Mar 2025PROJECT HAS BEEN DELAYED DUE TO PROMOTER MEDICAL CONDITION

Location, Land & Connectivity

Located at TITWALA, HARI OM VALLEY ROAD, Kalyan, Thane, 421605. Per the filed land record, the plot is bounded to the north by ROAD, to the south by ROAD, to the east by BUNGLOW and to the west by 9 M W DP ROAD. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

See every Vishnu Developers project & its RERA track record →

Other RERA-registered projects in Titwala

Indrayani
declared completion Oct 2026 · Naresh Yashwant Patil
Mantra
declared completion Nov 2026 · Vaidikh Nirmaan LLP
Rusttagi Aarambha 2.0
declared completion Nov 2026 · Rustagi Estates Private Limited
Ganpati Prasanna
declared completion Dec 2026 · Vijay Prabhakar Patil
Hillcrest Appartments
Registration suspended · declared completion Dec 2026 · Aasanghar Construction
Kalas Darshan
declared completion Dec 2026 · JAY Ganesh Developers
More projects in Thane

Other RERA-registered projects in Thane

Pardeshi Paradise
declared completion Jul 2023 · Vishnu Developers
Parijas Horizon
declared completion Jun 2028 · Octave Infraventures LLP
Parijatak Phase I A AND B Wing
declared completion Jun 2026 · Varad Builders
Parisparshs 23 Avenue
declared completion Mar 2026 · Parisparsh
Paritosh CO Operative Housing Society Limited
declared completion May 2026 · Not Available
Parivar Sadan CHS LTD
declared completion Mar 2027 · Kaivalya AND Associates

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.