Mumbai/Project record

MahaRERA · the public record

Parvati Complex

Pushpak New · Baban Laxman Mule

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Dec 2024declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for Parvati Complex

MahaRERA · P52000034322

Delivery and registration

When is the project declared for completion?

Parvati Complex is registered with MahaRERA as P52000034322 and the promoter has declared completion for 30 Dec 2024.

30 Dec 2024

declared completion

22months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP52000034322
Registered on04 Apr 2022
Promoter-declared completion30 Dec 2024
Current statusCertificate Signed
Against todayabout 22 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Parvati Complex record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Parvati Complex in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
Parvati Complex1G+731 Dec 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2024In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reas

Location, Land & Connectivity

Located at Pushpak New, Sector -24, Thane, Thane, 410206. Per the filed land record, the plot is bounded to the north by 11 Mtr Wide Raod, to the south by Plot No -386 and 387, to the east by Plot No -390 and to the west by Plot No -392. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Panvel

Shreeji Icon
declared completion Oct 2026 · Shreeji Lifespaces Group
Govind Ameya
declared completion Oct 2026 · Mansarovar Constructions
Shikara Greens Phase I
declared completion Oct 2026 · Shikara Constructions Pvt. Ltd.
Ambers Dnyaneshwar Capital
declared completion Nov 2026 · Capital Builders
Govind Greens
declared completion Nov 2026 · Priyal Buildcon LLP
Jupiter Royal
declared completion Nov 2026 · Arjun Ashok Tarachandani
More builders in Panvel

Major developers building in Panvel

More projects in Raigarh

Other RERA-registered projects in Raigarh

Parvati Heritage
declared completion Jun 2026 · R D Lifespace
Parvati Icon
declared completion Dec 2029 · R D Homes
Parvati Pride
declared completion Oct 2029 · R D Builders
Patel Aura
declared completion Aug 2026 · Mahavir Developers
Patel Heights
declared completion Sep 2022 · A S Enterprises
Patel Heritage
declared completion Dec 2027 · Patel Builders And Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.