RAJ REGALIA - PHASE I

AMBARNATH · AMRUT LAXMI DEVELOPERS

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Jun 2021declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for RAJ REGALIA - PHASE I

MahaRERA · P51700017364

Delivery and registration

When is the project declared for completion?

RAJ REGALIA - PHASE I is registered with MahaRERA as P51700017364 and the promoter has declared completion for 30 Jun 2021.

30 Jun 2021

declared completion

64months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51700017364
Registered on07 Aug 2018
Promoter-declared completion30 Jun 2021
Current statusCertificate Signed
Against todayabout 64 months past the declared date

Promoter record

What else is this promoter on record for?

AMRUT LAXMI DEVELOPERS is the promoter of record on 3 projects registered with MahaRERA.

3projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for RAJ REGALIA - PHASE I in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
GLAMOUR1G+1331 Dec 2020
GLITTER1G+1331 Dec 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2022As you are aware, the current Covid-19 situation. Due to the Lockdown work that is blocked, we are not able to give possession at 30/06/2021. That’swhy we ask to you kindly extend

Location, Land & Connectivity

Located at AMBARNATH, PALE VILLAGE SHIV MANDIR ROAD, Ambarnath, Thane, 421501. Per the filed land record, the plot is bounded to the north by 24 MT DP ROAD, to the south by S NO 54 H NO 3 P 5, to the east by S NO 55 H NO 1 and to the west by S NO 54 H NO 2. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Ambernath

Meera Nanda Bliss
declared completion Nov 2026 · Meera Homes LLP
Raj Residency
declared completion Nov 2026 · Vijay Chahu Patil
Precious Empire Wing A, B AND C
declared completion Dec 2026 · RKR Reality
Chaitraban CHS
declared completion Dec 2026 · Annapurna Enterprises
Dipti Skycity Bldg No. 7
declared completion Dec 2026 · Dipti Home Makers Pvt Ltd
Imperial Heights
declared completion Dec 2026 · Krishna Developers
More builders in Ambernath

Major developers building in Ambernath

More projects in Thane

Other RERA-registered projects in Thane

RAJ Residency
declared completion Dec 2021 · Paragon Buildcon
Raj Residency
declared completion Nov 2026 · Vijay Chahu Patil
RAJ Residency
declared completion Dec 2029 · Ruturaj Builders
RAJ Silverstone Phase-2
declared completion Jul 2026 · Skyspace Builtek
RAJ Tattva Phase 1 Commercial
declared completion Dec 2025 · Kothari Autoparts Manufacturers PVT LTD
RAJ Torres Phase 1
declared completion Mar 2019 · Rajesh Estates AND Nirman PVT LTD

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 11 Sep 2026. Document and inventory dates are shown in their sections.