Mumbai/Project record

MahaRERA · the public record

Ramchandra Residency Building No. 2

chandansar · Himali Construction

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
31 Jul 2025declared completionMahaRERA registration · read 19 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 19 Jul 2026

Free project details

Registration read 19 Jul 2026

RERA details for Ramchandra Residency Building No. 2

MahaRERA · P99000024898

Delivery and registration

When is the project declared for completion?

Ramchandra Residency Building No. 2 is registered with MahaRERA as P99000024898 and the promoter has declared completion for 31 Jul 2025.

31 Jul 2025

declared completion

15months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 19 Jul 2026

MahaRERA registrationP99000024898
Registered on09 Mar 2020
Promoter-declared completion31 Jul 2025
Current statusCertificate Signed
Against todayabout 15 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Ramchandra Residency Building No. 2 record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 19 Jul 2026

View the free 14-item checklist →

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (2025-06-30).

Promoter record

What else is this promoter on record for?

Himali Construction is the promoter of record on 2 projects registered with MahaRERA.

2projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 19 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Ramchandra Residency Building No. 2 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 19 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
Ramchandra Residency Bldg no 21G+8-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered31 Jul 2024We M/s. Himali Construction are constructing a building known as “Ramchandra Residency, Building No. 2”, Situated at Survey No. 143, H. No. 3, Village Kopri, Taluka Vasai, District
31 Jul 202431 Jul 2025Reasons for Delay:Initially, the project received development permission for G+Stilt+7 floors. However, revised approval was granted for G+Stilt+8 floors. This adjustment necessita

Location, Land & Connectivity

Located at chandansar, kopri village road , Vasai, Palghar, 401305. Per the filed land record, the plot is bounded to the north by sani mandir, to the south by om sai siddhivinayak bldg, to the east by Kopri village road and to the west by metha pharma office. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 140 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Powai / Hiranandani business park140 km
Andheri MIDC / SEEPZ141 km
Chhatrapati Shivaji Int'l Airport145 km
Bandra Kurla Complex (BKC)147 km
Lower Parel / Worli business district156 km
Nariman Point / Fort163 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Virar East

Viva Haritara Building-3/wing-B
Deregistered by MahaRERA · declared completion Dec 2026 · Vivaholdings
Jivdani Mauli
Not filing quarterly progress reports · declared completion Dec 2026 · Kiran Ramesh Patil
Mahavir Ashish CO-Operative Housing Society LTD
declared completion Dec 2026 · Yashraj Developers
Raajlaxmi Avenue
declared completion Dec 2026 · Magnus Infracon
Radheya Enterprises
declared completion Dec 2026 · Divesh Ratilal Shah
SAI Baba Nagar
declared completion Dec 2026 · VED Ganga
More projects in Palghar

Other RERA-registered projects in Palghar

Ramchandra Sankul
declared completion Aug 2019 · Sai Rath Construction Co.
Ramesh Heights
declared completion Dec 2026 · S S Enterprises
Ramesh Heights Phase 1
declared completion Dec 2026 · SAI Vidya Construction
Ramesh Residency
declared completion Dec 2026 · AAR AAR Homes India Private Limited
Rameshwar
declared completion Jul 2026 · Chheda Associate
Rameshwar Arcade
declared completion Dec 2025 · Level Up Realtors

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.