RELIABLE SHREEJEE EMPIRE

Palghar · SAHARA SHREEJEE BUILDERS AND DEVELOPERS

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
25 Dec 2025declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for RELIABLE SHREEJEE EMPIRE

MahaRERA · P99000010571

Delivery and registration

When is the project declared for completion?

RELIABLE SHREEJEE EMPIRE is registered with MahaRERA as P99000010571 and the promoter has declared completion for 25 Dec 2025.

25 Dec 2025

declared completion

10months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP99000010571
Registered on31 Aug 2017
Promoter-declared completion25 Dec 2025
Current statusCertificate Signed
Against todayabout 10 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for RELIABLE SHREEJEE EMPIRE record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (2025-06-30).

Promoter record

What else is this promoter on record for?

SAHARA SHREEJEE BUILDERS AND DEVELOPERS is the promoter of record on 2 projects registered with MahaRERA.

2projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for RELIABLE SHREEJEE EMPIRE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12.

BuildingWingsFloorsDeclared completion
G AND H WING1G+1230 Dec 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2021we are waiting for environment clearance certificate which is under process as applied by land owner after receiving we will apply occupation certificate, as of now we have given s
31 Dec 202125 Dec 2025DUE TO DELAY IN NEW CC WE NEED EXTENSION.

Location, Land & Connectivity

Located at Vasai, Palghar, 401203. Per the filed land record, the plot is bounded to the north by LAYOUT RG, to the south by DP ROAD, to the east by ADJ SURVEY NO 184 and to the west by PHASE I SEC I E F WING. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 33 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Andheri MIDC / SEEPZ33 km
Powai / Hiranandani business park35 km
Chhatrapati Shivaji Int'l Airport37 km
Bandra Kurla Complex (BKC)40 km
Lower Parel / Worli business district47 km
Nariman Point / Fort55 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Nallasopara West

Kunal Height
declared completion Dec 2026 · Shree SAI Builders & Developers
Vimal Classic
declared completion Dec 2026 · OM Vimal Developers
Anant Tower E AND F
declared completion Dec 2026 · Shantinath Enterprises
Dhananjay Avenue
declared completion Dec 2026 · SAI Kiran Builder AND Developers
Sai Baba Nagar Residential With Shopline Building With A B C Wings
Not filing quarterly progress reports · declared completion Dec 2026 · Shreeji Associates
Baba SAI Palce CO-OP-HSG LTD
declared completion Dec 2026 · G R AND Sons
More projects in Palghar

Other RERA-registered projects in Palghar

Reliable Shreejee Empire Phase II
declared completion Dec 2019 · Sahara Shreejee Builders AND Developers
Reliable Swapna Nagri-9,10,11,12
declared completion Dec 2025 · Reliable Tarang
Reliable Township / RT- A, B Wing
declared completion Dec 2018 · Reliable Realtors
Renuka Apartment-Type F
declared completion Dec 2024 · Space Enterprises
Renuka Appartment Type G
declared completion Apr 2027 · Aaryan Singh
Renuka Complex
declared completion Sep 2023 · Anupam A Giri

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.