Mumbai/Project record

MahaRERA · the public record

RUDRA APARTMENT

MIRAROAD EAST · SHREENATH CONSTRUCTIONS

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Mar 2024declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for RUDRA APARTMENT

MahaRERA · P51700033763

Delivery and registration

When is the project declared for completion?

RUDRA APARTMENT is registered with MahaRERA as P51700033763 and the promoter has declared completion for 30 Mar 2024.

30 Mar 2024

declared completion

31months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51700033763
Registered on08 Mar 2022
Promoter-declared completion30 Mar 2024
Current statusCertificate Signed
Against todayabout 31 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for RUDRA APARTMENT record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Promoter record

What else is this promoter on record for?

SHREENATH CONSTRUCTIONS is the promoter of record on 4 projects registered with MahaRERA.

4projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for RUDRA APARTMENT in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
RUDRA APARTMENT1G+831 May 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Mar 2024DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION FOR 12 MONTHS

Location, Land & Connectivity

Located at MIRAROAD EAST, DEEPAK HOSPITAL LANE INDRALOK, Borivali, Mumbai Suburban, 401105. Per the filed land record, the plot is bounded to the north by 18 MT WIDE DP ROAD, to the south by DURGA HEIGHT, to the east by SHUBHCHINTAK HEIGHT and to the west by DP ROAD. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bhayander East

Gayatri Elegance
declared completion Dec 2026 · Gayatrikripa Developers Private Limited
Basera Heights
declared completion Dec 2026 · Kamruddin Hasmullah Siddique
Durga Enclave
declared completion Dec 2026 · Anmol Developers
Ranuja Ramdev C Type
declared completion Dec 2026 · Ranuja Ramdev C Type
Surya Heritage A
declared completion Dec 2026 · Arun Construction CO
The Pentagon
declared completion Dec 2026 · Anjani Kumar Realty Private Limited
More projects in Thane

Other RERA-registered projects in Thane

Rudra Apartment
declared completion Jul 2027 · Indoria & Sons Realtors LLP
Rudra Avenue
declared completion Dec 2028 · Krivi Construction
Rudra Heights
declared completion Dec 2024 · A.s.d. Enterprises
Rudra Infra
declared completion Apr 2024 · MS Rudra Infra THR Porp Amol B Kaduskar
Rudra Residency
declared completion Aug 2028 · S R Choudhari Construction
Rudra VAN
declared completion Dec 2025 · Shivkrupa Realty

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.