Mumbai/Project record

MahaRERA · the public record

RUDRA HEIGHTS

Mumbai Suburban · SWAYAM DEVELOPERS

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
31 Dec 2023declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for RUDRA HEIGHTS

MahaRERA · P51800005195

Delivery and registration

When is the project declared for completion?

RUDRA HEIGHTS is registered with MahaRERA as P51800005195 and the promoter has declared completion for 31 Dec 2023.

31 Dec 2023

declared completion

34months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51800005195
Registered on10 Aug 2017
Promoter-declared completion31 Dec 2023
Current statusCertificate Signed
Against todayabout 34 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for RUDRA HEIGHTS record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Promoter record

What else is this promoter on record for?

SWAYAM DEVELOPERS is the promoter of record on 2 projects registered with MahaRERA.

2projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for RUDRA HEIGHTS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+23.

BuildingWingsFloorsDeclared completion
RUDRA HEIGHTS A AND B WING1G+2301 Jul 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 4 times, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2021Due to the Current Pandemic situation and lower availability of laborers, we seek extension up to 30/06/2021
30 Jun 202131 Dec 2021LACK IN FRENQUENCY FOR AVAILABILITY OF MATERIAL & LABORERS
31 Dec 202130 Jun 2022Our Project is ready and we are in the process of application for occupation certificate. conditions required for occupation certificate is also obtained. parking work in progress.
30 Jun 202231 Dec 2023DELAY IN PARKING TOWER . PART COMPLETION OF CFO IS ALREADY OBTAINED. ALL OTHER COMPLIANCE ARE COMPLETED EXCEPT PARKING TOWER.

Location, Land & Connectivity

Located at Mumbai, Mumbai Suburban, 400067. Per the filed land record, the plot is bounded to the north by GOKUL GAURAV, to the south by FOOD FEEL CHAWL, to the east by ROAD 18 MTRS and to the west by ASSUMPTION HOUSE CHAWL. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 9 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Andheri MIDC / SEEPZ9 km
Powai / Hiranandani business park12 km
Chhatrapati Shivaji Int'l Airport13 km
Bandra Kurla Complex (BKC)16 km
Lower Parel / Worli business district23 km
Nariman Point / Fort31 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kandivali West

Goyal Aspire
declared completion Oct 2026 · Nexa Buildcon LLP
Kandivali Hanuman Co-Op Housing Society Ltd
declared completion Nov 2026 · Kandivali Hanuman Co-Op Housing Society
Avenue Wing B
declared completion Dec 2026 · Dharmesh Constructions Private Limited
RAM Chhaya
Not filing quarterly progress reports · declared completion Dec 2026 · Prime Infra
Rock Highland
declared completion Dec 2026 · Rock Estates
Sale Bldg NO. 6 Wing Known AS Northern Supremus & Northern Hills Building NO. 1 & 2
declared completion Dec 2026 · N.rose Developers PVT LTD
More projects in Mumbai Suburban

Other RERA-registered projects in Mumbai Suburban

Rudra Paradise
declared completion Jul 2026 · R-Stone Design And Build Limited
Rudra Residency
declared completion Dec 2029 · Rudra Infrarealty LLP
Rudra Starlight
declared completion Jul 2029 · RT Housing Private Limited
Rudraksh Heritage Wing A AND Wing B
declared completion Mar 2023 · S Square Developers
Rudraksh Towers Wing A
declared completion Dec 2029 · AVS Housing AND Construction LLP
Rudraksh Towers Wing B
declared completion Dec 2029 · AVS Housing AND Construction LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.