SANSKRUTI HEIGHTS

Palghar · SHREE SANSKRUTI BUILDERS AND DEVELOPERS

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Mar 2023declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for SANSKRUTI HEIGHTS

MahaRERA · P99000008380

Delivery and registration

When is the project declared for completion?

SANSKRUTI HEIGHTS is registered with MahaRERA as P99000008380 and the promoter has declared completion for 30 Mar 2023.

30 Mar 2023

declared completion

43months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP99000008380
Registered on18 Aug 2017
Promoter-declared completion30 Mar 2023
Current statusCertificate Signed
Against todayabout 43 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SANSKRUTI HEIGHTS record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Promoter record

What else is this promoter on record for?

SHREE SANSKRUTI BUILDERS AND DEVELOPERS is the promoter of record on 2 projects registered with MahaRERA.

2projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SANSKRUTI HEIGHTS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
WING A C D AND E1G+715 Jul 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered14 Jul 2020DUE CHANGE IN ENVIRONMENT NORMS OCCUPANCY CERTIFICATE HAS BEEN DELAYED.
14 Jul 202030 Sep 2022DUE TO CURRENT ONGOING COVID 19 PANDEMIC AND SHORTAGE OF DAILY LABOUR WE ARE UNABLE TO ACHIVE THE COMPLETION DATE AND REQUIRE MORE TIME TO COMPLETE AND SALE THE ENTIRE PROJECT/FLAT

Location, Land & Connectivity

Located at Vasai, Palghar, 401203. Per the filed land record, the plot is bounded to the north by INTERNAL ROAD, to the south by BLDG NO 5 WING F AND G, to the east by ADJ S NO 259 and to the west by PHASE 1 SECTOR 5 BLDG 4. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 34 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Andheri MIDC / SEEPZ34 km
Powai / Hiranandani business park36 km
Chhatrapati Shivaji Int'l Airport38 km
Bandra Kurla Complex (BKC)41 km
Lower Parel / Worli business district48 km
Nariman Point / Fort56 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Nallasopara West

Kunal Height
declared completion Dec 2026 · Shree SAI Builders & Developers
Vimal Classic
declared completion Dec 2026 · OM Vimal Developers
Anant Tower E AND F
declared completion Dec 2026 · Shantinath Enterprises
Dhananjay Avenue
declared completion Dec 2026 · SAI Kiran Builder AND Developers
Sai Baba Nagar Residential With Shopline Building With A B C Wings
Not filing quarterly progress reports · declared completion Dec 2026 · Shreeji Associates
Baba SAI Palce CO-OP-HSG LTD
declared completion Dec 2026 · G R AND Sons
More projects in Palghar

Other RERA-registered projects in Palghar

Sanskruti Paradise
declared completion Apr 2029 · Sanskruti Venture
Sanskruti Pinnacle
declared completion Jul 2029 · Sanskruti Developer
Sanskruti Pride
declared completion Dec 2029 · Sanskruti Construction Co.
Sanskruti Rose
declared completion Dec 2027 · Sanskruti Builder AND Developer
Sanskruti Sapphire
declared completion Dec 2027 · Sanskruti Builder AND Developer
Sanskruti Solitaire
declared completion Dec 2026 · Sanskruti Builder & Developer

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.