Ambivali Andheri West · Meghna Infracon Infrastructure Limited

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
25 Dec 2029declared completionMahaRERA registration · read 19 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 19 Jul 2026

Free project details

Registration read 19 Jul 2026

RERA details for Shree Pranam

MahaRERA · PR1180002500220

Delivery and registration

When is the project declared for completion?

Shree Pranam is registered with MahaRERA as PR1180002500220 and the promoter has declared completion for 25 Dec 2029.

25 Dec 2029

declared completion

38months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 19 Jul 2026

MahaRERA registrationPR1180002500220
Registered on04 Jul 2025
Promoter-declared completion25 Dec 2029
Current statusCertificate Signed
Against today38 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Shree Pranam record 2 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 19 Jul 2026

  • Filing progress reports — 2 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Meghna Infracon Infrastructure Limited is the promoter of record on 3 projects registered with MahaRERA.

3projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 19 Jul 2026

Construction

How much construction cost has been reported?

In Shree Pranam, ₹2.70 Cr of a declared ₹22.95 Cr estimated project cost is reported as incurred, about 11.8%, as at the last certified filing with MahaRERA.

11.8%

₹2.70 Cr

of ₹22.95 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 19 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Shree Pranam in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 19 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+1.

BuildingWingsFloorsDeclared completion
Shree Pranam1G+1-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Ambivali Andheri West, *, Borivali, Mumbai Suburban, 400053. Per the filed land record, the plot is bounded to the north by C.T.S. No-833/95, to the south by C.T.S. No-833/93, to the east by C.T.S. No-833/87 and to the west by 9.15M Wide Existing Road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 5 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Andheri MIDC / SEEPZ5 km
Chhatrapati Shivaji Int'l Airport7 km
Powai / Hiranandani business park9 km
Bandra Kurla Complex (BKC)9 km
Lower Parel / Worli business district15 km
Nariman Point / Fort23 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Andheri West

ARC ONE
declared completion Dec 2026 · Chandra Gupta Estates Private Limited
MDM Maestro
declared completion Dec 2026 · MDM Realty LLP
Platinum Grandeur
declared completion Dec 2026 · Platinum Strategic Developers LLP
Tapodhan
declared completion Dec 2026 · Gurukul Realty LLP
Vengurlekars Chaitra
declared completion Dec 2026 · Vengurlekars Shreesai Builders And Devel
Gurukrupa Dhyanam
declared completion Mar 2027 · Gurukrupa Realcon Infrabuild LLP
More builders in Andheri West

Major developers building in Andheri West

More projects in Mumbai Suburban

Other RERA-registered projects in Mumbai Suburban

Shree Raam Residency
declared completion Jun 2028 · Antariksh Developers
Shree Radhe Shyam Heights
declared completion Dec 2027 · Shree SAI Builders
Shree Ram Residency
declared completion Dec 2026 · Elite Housing LLP
Shree Sadhana Co-Operative Housing Society Limited
declared completion Dec 2029 · Shree Sadhana Co-Operative Housing Socie
Shree SAI Mahal
declared completion Dec 2028 · Allstream Constructions Private Limited
Shree Sai Prasad SRA CHS LTD
declared completion Sep 2020 · Arjun Anant Waghmare

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.