Developer RERA record

Runwal

Runwal has 85 RERA-registered projects: 51 projects under construction; 34 projects past their declared completion date — a significant track-record flag. All figures are the developer's own regulator filings.

On the register
Delivery signal
51
Under construction
34
Past declared date

Under construction

Under construction — 51 projects

Construction % is the developer's own latest quarterly filing (Bengaluru, Gurgaon, Noida); MahaRERA files no construction %, so its projects show the declared possession date.

ProjectCityProgress / possession
25hourlife - Tower A1Mumbaipossession by Dec 2030
25hourlife - Tower B1Mumbaipossession by Dec 2029
25hourlife - Tower C1Mumbaipossession by Dec 2029
7 Mahalaxmi - Tower 1Mumbaipossession by Oct 2031
7 Mahalaxmi - Tower 2Mumbaipossession by Oct 2031
7 Mahalaxmi - Tower 3Mumbaipossession by Sep 2034
Code Name-EnchantedMumbaipossession by Jun 2028
Runwal Avenue Wing - IMumbaipossession by Apr 2028
Runwal Avenue Wing - LMumbaipossession by Dec 2027
Runwal Avenue Wing - MMumbaipossession by Oct 2028
Runwal Avenue Wing - NMumbaipossession by Dec 2027
Runwal Avenue Wing KMumbaipossession by Jun 2027
Runwal Avenue Wing-JMumbaipossession by Jun 2027
Runwal Bliss - Wing FMumbaipossession by Jul 2029
Runwal Bliss - Wing GMumbaipossession by Dec 2027
Runwal Bliss - Wing HMumbaipossession by Jun 2028
Runwal DreamsMumbaipossession by Dec 2027
Runwal EdgeMumbaipossession by Sep 2027
Runwal Forests Tower 9 - 11Mumbaipossession by Jun 2027
Runwal Garden City Cluster 11 Tower 1-2Mumbaipossession by Jul 2032
Runwal Garden City Cluster 6 Tower 6 To 9Mumbaipossession by Mar 2029
Runwal Gardens - Phase 8 - Bldg No. 44Mumbaipossession by Mar 2027
Runwal Gardens Phase 4 Bldg No. 31-32Mumbaipossession by Dec 2026
Runwal Gardens Phase 4 Bldg No. 33-34Mumbaipossession by Sep 2026
Runwal Gardens Phase 4 Bldg No. 35-36Mumbaipossession by Mar 2027
Runwal Gardens Phase 4 Bldg No. 37Mumbaipossession by Jun 2027
Runwal Gardens Phase 4 Bldg No. 38Mumbaipossession by Dec 2027
Runwal Gardens Phase 5 Bldg No. 39 To 42Mumbaipossession by Jun 2028
Runwal Gardens Phase 6A Bldg No. 53-54Mumbaipossession by Jun 2029
Runwal Gardens Phase 8 Bldg No. 43 And 45Mumbaipossession by Dec 2026
Runwal Lands ENDMumbaipossession by Jun 2029
Runwal Lands END - BreezeMumbaipossession by Apr 2031
Runwal Lands End- SkyeMumbaipossession by Sep 2030
Runwal MalabarMumbaipossession by Jun 2032
Runwal Meadows-AsterMumbaipossession by Jul 2033
Runwal Meadows-DaisyMumbaipossession by Jul 2033
Runwal NexusMumbaipossession by Dec 2026
Runwal One- Tower D2Mumbaipossession by Jul 2031
Runwal One-Tower D1Mumbaipossession by Sep 2030
Runwal One-Tower EMumbaipossession by Jan 2031
Runwal PinnacleMumbaipossession by Dec 2028
Runwal Raaya - Tower 1Mumbaipossession by Dec 2032
Runwal Raaya - Tower 2Mumbaipossession by Dec 2032
Runwal Shopping Arcade 2 - R Galleria 2Mumbaipossession by Jun 2029
Runwal TimelessMumbaipossession by Sep 2026
Runwal Westwind HeightsMumbaipossession by Dec 2028
Runwal WoodsMumbaipossession by Sep 2028
The SanctuaryMumbaipossession by Jul 2028
THE Sanctuary - Tower 2Mumbaipossession by Mar 2027
UmedPunepossession by Jul 2026
ZenithMumbaipossession by Sep 2028
Considering a specific Runwal project? Tell us which one and we'll send you its full RERA record — completion certificate, construction history, quarterly updates.
Past declared date (34)click to expand

The declared completion date has passed with no completion certificate on record. Many projects receive RERA extensions, and MahaRERA publishes no OC at all — so this is the raw disclosure, not a verdict on delivery. Verify current status on the RERA portal.

ProjectCityDeclared date
Codename Rare BY RunwalMumbai2026-06
Nirvana Part IMumbai2024-12
Primrose Mhada 2Mumbai2025-03
Runwal Anthurium - ValentineMumbai2023-12
Runwal ArcadePune2020-12
Runwal Bliss Wing - AMumbai2023-12
Runwal Bliss Wing - CMumbai2023-12
Runwal Bliss Wing - DMumbai2023-12
Runwal Bliss Wing - EMumbai2023-12
Runwal Bliss Wing -BMumbai2023-12
Runwal Commerz - Tower 1Mumbai2025-10
Runwal Eirene - Part IMumbai2025-06
Runwal Elegante - Tower AMumbai2023-12
Runwal ElinaMumbai2018-12
Runwal Elina Wing CMumbai2022-12
Runwal EmeraldPune2025-07
Runwal Forest Tower 1-4Mumbai2022-04
Runwal Forests Tower 5-8Mumbai2022-12
Runwal Garden City - DahliaMumbai2023-12
Runwal Gardens Phase 2 Bldg No 13-17Mumbai2025-06
Runwal Gardens Phase 2 Bldg No 18-23Mumbai2024-12
Runwal Gardens Phase 3 Bldg No 24-26Mumbai2025-06
Runwal Gardens Phase 3 Bldg No 27-28Mumbai2026-06
Runwal Gardens Phase 3 Bldg No 29-30Mumbai2026-06
Runwal Gardens Phase IMumbai2025-06
Runwal Greens Wings 5 - 8Mumbai2019-12
Runwal PearlMumbai2024-12
Runwal R-SquareMumbai2024-03
Runwal ReserveMumbai2019-12
Runwal SereneMumbai2019-05
Runwal Shopping ArcadeMumbai2025-04
THE ResidenceMumbai2020-12
THE Sanctuary - Tower 4Mumbai2026-06
THE Sanctuary - Tower 5Mumbai2026-03

Request the report on Runwal

We analyse Runwal in full and send you the RERA Property Intelligence Report — we analyse in 1 working day.

Something went wrong — email hello@quietlist.in instead.

Figures are Runwal's own disclosures on RERA registers, grouped to the consumer-facing developer brand. "Completed" means an OC is on the project's RERA record; construction % is the developer's latest quarterly filing. Past-deadline projects may have received extensions — always verify on the relevant RERA portal. See our market reports for context.