Not filing quarterly progress reports · declared completion Dec 2026 · M/s Shree Shantinagar Venture
Not filing quarterly progress reports · declared completion Dec 2026 · M/s Shree Shantinagar Venture
MahaRERA · the public record
Chinchpokli · Runwal Real Estates Private Limited
Project Review · example purchase
Spending a few crores on a home? ₹4,999 to check what you’re buying.
Check what the plans put beside your home, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.
From another project · Empire Solitaire
Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.
Read the Project Review sample ↗
From another project · Dosti Pine · earlier comprehensive example
E2506 has north-east-facing living space and a south-west entrance. E3001 reverses those directions and sits on the top floor. The report compares named flats, refuge adjacency and shared gardens using the March 2026 filing, read on 17 September 2026; this is not live availability.
This longer example shows the depth of research available in Project Deep Dive. These findings concern the named sample, not this project.
Read the Dosti Pine sample report ↗
Free project details
Registration read 19 Jul 2026MahaRERA · P51900079270
Delivery and registration
7 Mahalaxmi - Tower 2 is registered with MahaRERA as P51900079270 and the promoter has declared completion for 31 Oct 2031.
31 Oct 2031
declared completion
60months to go
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 19 Jul 2026
| MahaRERA registration | P51900079270 |
| Registered on | 25 Feb 2025 |
| Promoter-declared completion | 31 Oct 2031 |
| Current status | Certificate Signed |
| Against today | 60 months to the declared date |
Approvals and compliance
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for 7 Mahalaxmi - Tower 2 record 2 quarterly progress reports since registration.
2quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 19 Jul 2026
Promoter record
Runwal Real Estates Private Limited is the promoter of record on 3 projects registered with MahaRERA.
3projects
registered with MahaRERA
Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.
Source · MahaRERA register, all projects · read 19 Jul 2026
Construction
In 7 Mahalaxmi - Tower 2, ₹16.39 Cr of a declared ₹685.69 Cr estimated project cost is reported as incurred, about 2.4%, as at the last certified filing with MahaRERA.
2.4%
₹16.39 Cr
of ₹685.69 Cr declared cost
Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.
Source · MahaRERA quarterly progress filing · read 19 Jul 2026
Sales
In 7 Mahalaxmi - Tower 2, 49 of 150 homes filed with MahaRERA are recorded as sold or booked, about 33%, and 101 are filed as unsold.
33%sold or booked
49 of 150 homes
₹341.53 Cr
committed by buyers
Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹57.84 Cr (about 17%) is recorded as collected and ₹283.69 Cr as receivable.
Source · MahaRERA sold/unsold inventory filing · read 19 Jul 2026
Filed agreement values: across 49 sold or booked entries with usable filed values and areas, the effective carpet rate is ₹45,814/sqft, with eight in ten falling between ₹43,060 and ₹50,658 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.
No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.
Read from MahaRERA on 17 October 2026
MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for sold or booked entries the filed agreement value — the consideration filed for that specific home. On this project 49 homes carry one, and 101 of the 150 are recorded unsold.
Here is one home filed as unsold, beside the amounts filed for comparable homes:
| Home | Carpet | Filed comparison | Based on |
|---|---|---|---|
| T2-1203 | 1,318 sqft | Rs 6.13 cr typical, over Rs 5.58 cr to Rs 6.58 cr | 18 filed · similar area (within 2%), same building |
A filed consideration is the amount the promoter reported for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.
In 7 Mahalaxmi - Tower 2, 93 of the 101 unsold homes have filed sales to compare with. The Sales Report gives each of them its own row — the filed agreements behind its comparison listed in full, the government reckoner value the promoter filed against it, and mortgage status where the filing supplies it. Missing mortgage information is not confirmation that a unit is free of a mortgage. Built from the filing itself, sent by email.
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+83 and 150 homes are registered across the project.
| Building | Wings | Floors | Units | Declared completion |
|---|---|---|---|---|
| Tower - 2 | 1 | G+83 | 150 | - |
Unit mix on the filing: 150 residential.
No buyer complaints were on this project's MahaRERA record at the time of reading.
Located at Chinchpokli, N M Joshi Marg, Kurla, Mumbai Suburban, 400011. Per the filed land record, the plot is bounded to the north by CTS No 10-62 1E-62 1A-62, to the south by Sale Tower 1, to the east by Sale Tower 3 and to the west by Rehab Tower 2. These are the boundaries as recorded in the filed land record.
Free · Watch this project
We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.
Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.
Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.