Developer RERA record

Mahindra Lifespaces

Mahindra Lifespaces has 97 RERA-registered projects: strong Gurugram delivery record (2/3 projects with OC); 29 projects under construction, Bengaluru averaging 51% construction; 49 projects past their declared completion date. All figures are the developer's own regulator filings.

29
Under construction
4
Completed / delivered
49
Past declared date
83%
Bengaluru inventory booked
38
RERA complaints filed

Public registration records

These records have not been classified as delivered, under construction or overdue. The declared date and status are filings, not a current site inspection.

Aqualily Phase-2C2

Chennai region · Registered: 2022-05-20 · Declared completion: 2024-12-31

Lake Front Estates

Chennai region · Registered: 2023-06-28 · Declared completion: 2025-03-31

Happinest

Chennai region · Registered: 2020-02-13 · Declared completion: 2022-03-31

Happinest

Chennai region · Registered: 2021-09-01 · Declared completion: 2022-05-08

Under construction

Under construction — 29 projects

Construction % is the developer's own latest quarterly filing (Bengaluru, Gurgaon, Noida); MahaRERA files no construction %, so its projects show the declared possession date.

Pune: 1.65/5 ★★☆☆☆ (60 MouthShut reviews)

ProjectCityProgress / possession
MAHINDRA ZENBengaluru47%
MAHINDRA NEWHAVENBengaluru5%
MAHINDRA BLOSSOMBengaluru1%
Happinest Tathawade Phase-1Punepossession by Jan 2027
Mahindra BeaconhillMumbaipossession by Dec 2031
Mahindra Citadel - Bastion IPunepossession by Mar 2030
Mahindra Citadel - Bastion J , KPunepossession by Jun 2029
Mahindra Citadel - Phase 5Punepossession by Aug 2031
Mahindra Citadel - Tower LPunepossession by Dec 2030
Mahindra Citadel Phase 1Punepossession by Jun 2028
Mahindra Codename Crown Tower A And Tower BPunepossession by Mar 2030
Mahindra Codename Crown Tower EPunepossession by Mar 2030
Mahindra Happinest Kalyan - 2 Project BMumbaipossession by Dec 2028
Mahindra Happinest Kalyan-2 Project AMumbaipossession by Dec 2028
Mahindra Happinest Palghar 2 Phase 2Mumbaipossession by Feb 2027
Mahindra Happinest Tathawade Phase 2Punepossession by May 2027
Mahindra Happinest Tathawade Phase 3Punepossession by Dec 2027
Mahindra Ivylush Tower C And Tower DPunepossession by Aug 2030
Mahindra Marina64 - Phase 1Mumbaipossession by Dec 2029
Mahindra Marina64 - Phase 2Mumbaipossession by Dec 2029
Mahindra Marina64 - Phase 3Mumbaipossession by Jun 2030
Mahindra NestalgiaPunepossession by Aug 2027
Mahindra Rainforest Phase 1Mumbaipossession by Dec 2031
Mahindra Rainforest Phase 2Mumbaipossession by Dec 2031
Mahindra Rivenza Phase 1Punepossession by Dec 2031
Mahindra Rivenza Phase 2Punepossession by Dec 2031
Mahindra Vista Phase 1Mumbaipossession by Dec 2029
Mahindra Vista Phase 2Mumbaipossession by Dec 2030
Nest EWSPunepossession by Jan 2027
Considering a specific Mahindra Lifespaces project? Tell us which one and we'll send you its full RERA record — completion certificate, construction history, quarterly updates.
Delivered projects (4)click to expand
ProjectCityStatus
MAHINDRA EDEN PHASE-2Bengaluru100% built
MAHINDRA EDEN PHASE-1Bengaluru100% built
LUMINARE PHASE 2(SOLARIS)GurugramOC issued
LUMINARE PHASE I(SIRIUS)GurugramOC issued
Past declared date (49)click to expand

The declared completion date has passed with no completion certificate on record. Many projects receive RERA extensions, and MahaRERA publishes no OC at all — so this is the raw disclosure, not a verdict on delivery. Verify current status on the RERA portal.

ProjectCityDeclared date
Windchimes Phase 2Bengaluru2019-12
Windchimes Phase 1Bengaluru2018-12
LUMINARE PHASE 3 (TOWER B)Gurugram2026-08
Alcove Wing AMumbai2024-06
Alcove Wing BMumbai2024-06
Antheia B3Pune2020-09
Antheia C3Pune2023-03
Bloomdale Bloomdale 07Nagpur2022-09
Bloomdale Building 04Nagpur2018-03
Bloomdale Building 06Nagpur2021-12
Bloomdale Building 08Nagpur2020-09
Bloomdale Building 09Nagpur2020-09
Bloomdale Building 10 ANagpur2020-01
Bloomdale Building 10 BNagpur2017-05
Bloomdale Duplex 08 13 To 14Nagpur2020-02
Bloomdale Duplex Home 3Nagpur2018-09
Bloomdale Duplex Home 4Nagpur2019-12
Bloomdale Duplex Home 6Nagpur2022-03
Bloomdale Row House 11 55 To 60Nagpur2020-05
Bloomdale Row House 12 61 To 66Nagpur2021-09
Bloomdale Row House 5Nagpur2019-11
Bloomdale Row House 6Nagpur2019-11
Bloomdale Row House 7Nagpur2021-01
Bloomdale Row House 8 37 To 42Nagpur2022-01
Centralis Tower 4Pune2023-03
Centro MhadaPune2023-02
Mahindra Alcove Wing A AND CMumbai2026-06
Mahindra Alcove Wing BMumbai2025-12
Mahindra Bloomdale 4BNagpur2023-05
Mahindra Bloomdale 4CNagpur2022-09
Mahindra Happinest Kalyan Project BMumbai2025-06
Mahindra Happinest Palghar Phase - IMumbai2021-12
Mahindra Happinest Palghar Phase - IIIMumbai2022-09
Mahindra Happinest Palghar-2 Phase 1Mumbai2024-12
Mahindra Meridian PlotsMumbai2025-03
The Serenes Villa No 10Mumbai2022-12
The Serenes Villa No 11Mumbai2022-12
The Serenes Villa No 14Mumbai2022-12
The Serenes Villa No 16Mumbai2022-12
The Serenes Villa No 17Mumbai2022-12
The Serenes Villa No 19Mumbai2022-12
The Serenes Villa No 20Mumbai2022-12
The Serenes Villa No 21Mumbai2022-12
The Serenes Villa No 22Mumbai2022-12
The Serenes Villa No 4Mumbai2022-12
The Serenes Villa No 47Mumbai2022-12
The Serenes Villa No 7Mumbai2022-12
The Serenes Villa No 8Mumbai2022-12
The Serenes Villa No 9Mumbai2022-12

RERA complaints & orders

Regulatory record

38 total complaints filed — more complaints than 94% of builders we track.

28
MahaRERA complaints
10
Karnataka RERA complaints

Most recent orders on the RERA register:

ProjectComplainantBenchDate
Antheia B3Antheia Cooperative Housing Society Through its Chairman Mr. Manojkumar Babulal AgarwalHON. MEMBER IICopyright

Complaint counts and order records are sourced directly from RERA portals. A complaint is a filing by a buyer or association; an order is a formal ruling. Not all complaints lead to adverse orders. This is regulatory disclosure, not a verdict.

Figures are Mahindra Lifespaces's own disclosures on RERA registers, grouped to the consumer-facing developer brand. "Completed" means an OC is on the project's RERA record; construction % is the developer's latest quarterly filing. Past-deadline projects may have received extensions — always verify on the relevant RERA portal. See our market reports for context.