SHREE SADGURU COMPLEX BUILDING - 5

Washivali · EARTH HOME

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Jun 2027declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for SHREE SADGURU COMPLEX BUILDING - 5

MahaRERA · P52000020609

Delivery and registration

When is the project declared for completion?

SHREE SADGURU COMPLEX BUILDING - 5 is registered with MahaRERA as P52000020609 and the promoter has declared completion for 30 Jun 2027.

30 Jun 2027

declared completion

8months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP52000020609
Registered on26 Apr 2019
Promoter-declared completion30 Jun 2027
Current statusCertificate Signed
Against today8 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHREE SADGURU COMPLEX BUILDING - 5 record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (2025-06-30).

Promoter record

What else is this promoter on record for?

EARTH HOME is the promoter of record on 5 projects registered with MahaRERA.

5projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SHREE SADGURU COMPLEX BUILDING - 5 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
Building Number - 51G+531 Mar 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2027In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various r

Location, Land & Connectivity

Located at Washivali, Washivali, Panvel, Raigarh, 410220. Per the filed land record, the plot is bounded to the north by Grasslands, to the south by Savroli Kharpada Road, to the east by Parle Farm House and to the west by Gaothan. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 41 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Nariman Point / Fort40 km
Bandra Kurla Complex (BKC)41 km
Lower Parel / Worli business district41 km
Powai / Hiranandani business park41 km
Chhatrapati Shivaji Int'l Airport43 km
Andheri MIDC / SEEPZ45 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Washivali

Gurukrupa Heights
declared completion Dec 2026 · Gurukrupa Construction CO
Commanders Heera Siddhi Homes
declared completion Dec 2027 · Megaplex Properties LLP
Commanders Heera Siddhi Homes Phase III
declared completion Dec 2027 · Megaplex Properties LLP
Tulsi Kalash City Phase III
declared completion Mar 2028 · Trilok Properties Private Limited
Shree Sadguru Complex - Phase IV
Past its declared completion date · declared completion Dec 2022 · Earth Home
Shree Sadguru Complex - Phase III
Past its declared completion date · declared completion Dec 2021 · Earth Home
More projects in Raigarh

Other RERA-registered projects in Raigarh

Shree Sadguru Complex - Phase III
declared completion Dec 2021 · Earth Home
Shree Sadguru Complex - Phase IV
declared completion Dec 2022 · Earth Home
Shree Sadguru Krupa
declared completion Jun 2021 · Shree Sadguru Krupa
Shree Sadguru Krupa
declared completion Dec 2021 · Mahalaxmi Builders And Developers
Shree Sadguru Krupa
declared completion Dec 2021 · Avita Milind Gharat
Shree Sadguru Krupa
declared completion Dec 2027 · Sunil Bhiku Thombre

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.