Mumbai/Project record

MahaRERA · the public record

SPACE HOMES

VASAI EAST · SPACE HOMES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000022188

Delivery and registration

When is the project declared for completion?

SPACE HOMES is registered with MahaRERA as P99000022188 and the promoter has declared completion for 31 Dec 2022.

31 Dec 2022

declared completion

45months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000022188
Registered on05 Sep 2019
Promoter-declared completion31 Dec 2022
Current statusCertificate Signed
Against todayabout 45 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SPACE HOMES record 14 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 14 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SPACE HOMES in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+23.

BuildingWingsFloorsDeclared completion
MAJESTY1G+2330 Jun 2021
MONARCH1G+1630 Jun 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2022DUE TO COVID-19 WORK IS GOING ON SLOWLY

Location, Land & Connectivity

Located at VASAI EAST, VASAI NALLASOPARA LINK ROAD, Vasai, Palghar, 401209. Per the filed land record, the plot is bounded to the north by SECTOR 6 BUILDING NO 3 WING G AND H, to the south by SECTOR BUILDING NO 4 WING D, to the east by SECTOR 6 BUILDING NO 5 WING E and to the west by 16 METER WIDE INTERNAL ROAD. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Nallasopara East

Model Cooperative Housing Society LTD
possession by Oct 2026 · Sai Vaishnav Infra Llp
N G Platinum City
possession by Dec 2026 · J M G Realtors PVT LTD
Rudra Heights Bldg NO 1 Wing -G
possession by Dec 2026 · Aura Navkar Developers
Ajay CO-Operative Housing Society LTD
possession by Dec 2026 · MAA Guru Construction
Imperialparamount
possession by Dec 2026 · Shivganga Construction & Redeveloper
Precilla CHS LTD
possession by Dec 2026 · Blue OAK Infrastructure

Other RERA-registered projects in Palghar

Space ONE
possession by Dec 2026 · Space Square Constructions
Spanish Residency
declared completion Apr 2024 · Shantee Realty AND Life Space
Spanish Villa
declared completion Jun 2022 · Shantee Realty AND Life Space
Spanish Villa
declared completion Dec 2025 · Shantee Realty AND Life Space
Spanish Villa
possession by Dec 2027 · Shantee Realty AND Life Space
Spring Field
possession by Dec 2030 · Shantee Homes Realty LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 15 Sep 2026