Mumbai/Project record

MahaRERA · the public record

SWIZ HEIGHTS PHASE 2

ANDHERI WEST · Mohid Construction Co

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
31 Dec 2025declared completionMahaRERA registration · read 19 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 19 Jul 2026

Free project details

Registration read 19 Jul 2026

RERA details for SWIZ HEIGHTS PHASE 2

MahaRERA · P51800033525

Delivery and registration

When is the project declared for completion?

SWIZ HEIGHTS PHASE 2 is registered with MahaRERA as P51800033525 and the promoter has declared completion for 31 Dec 2025.

31 Dec 2025

declared completion

10months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 19 Jul 2026

MahaRERA registrationP51800033525
Registered on22 Feb 2022
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 10 months past the declared date

Promoter record

What else is this promoter on record for?

Mohid Construction Co is the promoter of record on 3 projects registered with MahaRERA.

3projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 19 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SWIZ HEIGHTS PHASE 2 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 19 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+9.

BuildingWingsFloorsDeclared completion
SWIZ HEIGHTS PHASE 21G+9-

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for SWIZ HEIGHTS PHASE 2, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 19 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000037524318/04/2023Nasrin Asif Shaikh vs Mohid Construction Co.order passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2023DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION FOR 12 MONTHS
31 Dec 202331 Dec 2024Due to shortage of raw materials and labor we are not able to complete project on time. Please grant us extension until 31 December 2024.
31 Dec 202431 Dec 2025That our above project is a SRA project with two phases therein for sale component and SWIZ HEIGHTS phase 2 had expired on 30.12.2024 . That in the month of April 2024, we have rec

Location, Land & Connectivity

Located at ANDHERI WEST, FOUR BUNGLOWS LOKHANDWALA COMPLEX, Andheri, Mumbai Suburban, 400053. Per the filed land record, the plot is bounded to the north by CTS 825 PART, to the south by D P ROAD 18-3, to the east by CTS 825C 825D and to the west by 27-45 METER ROAD JUNCTION. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Andheri West

ARC ONE
declared completion Dec 2026 · Chandra Gupta Estates Private Limited
MDM Maestro
declared completion Dec 2026 · MDM Realty LLP
Platinum Grandeur
declared completion Dec 2026 · Platinum Strategic Developers LLP
Tapodhan
declared completion Dec 2026 · Gurukul Realty LLP
Vengurlekars Chaitra
declared completion Dec 2026 · Vengurlekars Shreesai Builders And Devel
Gurukrupa Dhyanam
declared completion Mar 2027 · Gurukrupa Realcon Infrabuild LLP
More builders in Andheri West

Major developers building in Andheri West

More projects in Mumbai Suburban

Other RERA-registered projects in Mumbai Suburban

Tagore Nagar Anjali CHS Ltd
declared completion Dec 2024 · Aditya Enterprises
Tagore Nagar Nandadeep CHS Ltd
declared completion Dec 2023 · Samarth Krupa Developers
Taiba Residency
declared completion Dec 2029 · H M International
Tandice69
declared completion Dec 2024 · Right Channel Construction PVT LTD
Tanishkaa Vikrant
declared completion Jun 2029 · Tanishka Reality LLP
Tanishq Residency
declared completion Dec 2025 · Prathamesh Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.