VAIBHAV HEIGHTS

NEAR JAIN MANDIR · RSN BALAJI REALTORS P LTD

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

0units filed as unsoldInventory · 19 October 2026
30 Dec 2026declared completionMahaRERA registration · read 18 Jul 2026
52registered unitsMahaRERA registration · read 18 Jul 2026

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗

Free project details

Registration read 18 Jul 2026

RERA details for VAIBHAV HEIGHTS

MahaRERA · P51800002862

Delivery and registration

When is the project declared for completion?

VAIBHAV HEIGHTS is registered with MahaRERA as P51800002862 and the promoter has declared completion for 30 Dec 2026.

30 Dec 2026

declared completion

2months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51800002862
Registered on04 Aug 2017
Promoter-declared completion30 Dec 2026
Current statusCertificate Signed
Against today2 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for VAIBHAV HEIGHTS record 1 quarterly progress report since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

  • Filing progress reports — 1 quarterly progress report on record since registration, with no current default.

Sales

How many are filed as sold or booked?

In VAIBHAV HEIGHTS, 52 of 52 units filed with MahaRERA are recorded as sold or booked, about 100%, and 0 are filed as unsold.

100%sold or booked

52 of 52 units

₹51.24 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹50.55 Cr (about 99%) is recorded as collected and ₹69.02 Lakh as receivable.

Source · MahaRERA sold/unsold inventory filing · read 18 Jul 2026

Filed agreement values: across 52 sold or booked entries with usable filed values and areas, the effective carpet rate is ₹19,534/sqft, with eight in ten falling between ₹15,062 and ₹23,082 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, unit by unit

Read from MahaRERA on 19 October 2026

MahaRERA publishes, unit by unit, what this promoter filed: which units are sold and which are not, the RERA carpet area of each, and for sold or booked entries the filed agreement value — the consideration filed for that specific unit. On this project 52 units carry one, and Every unit on the filing is recorded sold or booked.

A filed consideration is the amount the promoter reported for one unit. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the unit is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

This snapshot marks all units in VAIBHAV HEIGHTS as sold or booked. It does not establish current availability. The filed values can still help you compare a quote. The Sales Report lists the 52 sold or booked entries with filed values: each unit, its carpet area, the consideration filed against it and the rate that works out to. Built from the filing itself, sent by email.

See all 52 filed sold/booked entries — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+14 and 52 units are registered across the project.

BuildingWingsFloorsUnitsDeclared completion
A WING CHOKSI APT REHAB1G+149-
B WING VAIBHAV HEIGHTS1G+1443-

Unit mix on the filing: 48 residential and 4 non-residential.

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for VAIBHAV HEIGHTS, with orders passed in 2 of them.

2complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000019885329/10/2021CORRINDA MIRANDA vs M/S RSN BALAJI REALTORS (P) LTDorder passed
CC00600000059113712/07/2024SANJAY SINGH vs RSN BALAJI REALTORS P LTDorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 5 times, as recorded on the register.

FromExtended toStated reason
as registered30 Apr 2020Due to awaiting implementation of DCPR 2034 and road TDR policy in connection to DCPR 2034, no file was being processed by MCGM for concession and issue of further CC. Thus due to
30 Apr 202030 Apr 20201) Ours is an ongoing project on land bearing CTS No. 3929 to 3949 proposed for 14th floors. We have completed work up till 12th floor having achieved height of 42.83 AMSL. We are
30 Apr 202030 Jun 2023Due to Promoters RSN Balaji Realtors has received NOC from Airport Authority of India (AAI), vide their letter no. BT-1/NOC/ CS/MUM/13/NOCAS/391 dated 9/5/2014. This NOC is firstl
30 Jun 202331 Dec 2024DUE TO COVID 19 NOT ABLE TO COMPLETE PROJECT PLEASE GRANT US EXTENSION TILL 31/12/2024
31 Dec 202430 Dec 2026The Project was Delay Due to awaiting implementation of DCPR 2034 and road policy in connection to DCPR 2034 and also because of getting Revalidations of NOC from civil aviation au

Location, Land & Connectivity

Located at NEAR JAIN MANDIR, SHIVAJI NAGAR ROAD, Andheri, Mumbai Suburban, 400055. Per the filed land record, the plot is bounded to the north by CTS NO 3928, to the south by CTS NO 7627, to the east by ROAD and to the west by D P ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 2 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Chhatrapati Shivaji Int'l Airport2 km
Bandra Kurla Complex (BKC)2 km
Andheri MIDC / SEEPZ6 km
Powai / Hiranandani business park7 km
Lower Parel / Worli business district9 km
Nariman Point / Fort17 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Santacruz East

Crystal Avenue
declared completion Nov 2026 · Eternia Realty
Ambit Vista
declared completion Dec 2026 · Ambit Builders & Developers
Atmiya Centria
declared completion Dec 2026 · Upturn Properties LLP
Crescent Nexus
declared completion Dec 2026 · Ascent Infraspace Private Limited
Crescent Nexus- Ascent C Wing
declared completion Dec 2026 · Ascent Infraspace Private Limited
Maitri Enclave
declared completion Dec 2026 · Atharva Enterprises
More projects in Mumbai Suburban

Other RERA-registered projects in Mumbai Suburban

Vaibhav Seasons
declared completion Mar 2030 · Vaibhav Construction
Vaibhavlaxmi Bramhand
declared completion Dec 2031 · Vaibhav Laxmi Builders & Developers
Vaibhavlaxmi Rhythm 51
declared completion Aug 2031 · V Laxmi SAI Prasad Developers LLP
Vaidya Cottage CHS Ltd
declared completion Oct 2021 · Shamik Enterprises Pvt Ltd.
Vaidya West World - Harmony
declared completion Jul 2027 · Vaidya Spaces Private Limited
Vaidya West World -ONE Aeropolis
declared completion Jun 2028 · Vaidya Spaces Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.