Mumbai/Project record

MahaRERA · the public record

YASH REALITY

OPP RAILWAY FOOT OVER BRIDGE · YASH REALITY

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000026224

Delivery and registration

When is the project declared for completion?

YASH REALITY is registered with MahaRERA as P99000026224 and the promoter has declared completion for 30 Jun 2023.

30 Jun 2023

declared completion

39months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000026224
Registered on30 Aug 2020
Promoter-declared completion30 Jun 2023
Current statusCertificate Signed
Against todayabout 39 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for YASH REALITY record 12 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 12 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for YASH REALITY in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
MANU - KRUPA1G+531 Dec 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at OPP RAILWAY FOOT OVER BRIDGE, MANVELPADA ROAD, Vasai, Palghar, 401305. Per the filed land record, the plot is bounded to the north by STATION ROAD, to the south by S NO 252 H NO 2, to the east by INTERNAL ROAD and to the west by MANVELPADA ROAD. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Virar East

Viva Haritara Building-3/wing-B
Deregistered by MahaRERA · possession by Dec 2026 · Vivaholdings
Jivdani Mauli
Not filing quarterly progress reports · possession by Dec 2026 · Kiran Ramesh Patil
Mahavir Ashish CO-Operative Housing Society LTD
possession by Dec 2026 · Yashraj Developers
Raajlaxmi Avenue
possession by Dec 2026 · Magnus Infracon
Radheya Enterprises
possession by Dec 2026 · Divesh Ratilal Shah
SAI Baba Nagar
possession by Dec 2026 · VED Ganga

Other RERA-registered projects in Palghar

Yashoda Apartment
possession by Dec 2026 · Panchavati Builders AND Developers
Yashoda Heritage
possession by Feb 2027 · OM Nityanand Construction
Yashodhan
possession by Dec 2028 · Fia Developers Pvt. Ltd.
Yashvant Pride
declared completion Dec 2022 · SAI Swapn Developer
Yashvi Pride
possession by Dec 2027 · Yashvi Pride LLP
Yashvi Pride Building No.3 Wing-O
possession by Dec 2027 · Yashvi Pride LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 15 Sep 2026