Nagpur/Project record

MahaRERA · the public record

RAJ PALACE XI

Besa · SSV BUILDERS & DEVELOPERS

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
31 Mar 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

Free project details

Registration read 12 Jul 2026

RERA details for RAJ PALACE XI

MahaRERA · P50500031463

MahaRERA Record Signals

The regulator-filed signals we track for this project from the MahaRERA record.

  • Construction: ~100.0% of the estimated cost incurred, per the MahaRERA cost filing.

Delivery and registration

When is the project declared for completion?

RAJ PALACE XI is registered with MahaRERA as P50500031463 and the promoter has declared completion for 31 Mar 2024.

31 Mar 2024

declared completion

31months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP50500031463
Promoter-declared completion31 Mar 2024
Current statusCertificate Signed
Against todayabout 31 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for RAJ PALACE XI record 10 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 10 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for RAJ PALACE XI in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Location, Land & Connectivity

Located at Besa, Nagpur. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Besa

Aarish Residency
Not filing quarterly progress reports · declared completion Dec 2026 · Aarish Infrastructure
Sonestaa
declared completion Dec 2026 · Inches Realities
Kaushalya Nagari
declared completion Feb 2027 · Dhage Builders
Meeramadhav Height
declared completion Mar 2027 · Not Available
Royal Dream City-2
declared completion Dec 2027 · Shriniwasa Builders & Developers LLP
Shree Laxmi Peace City
declared completion Dec 2027 · Shree Laxmi Venture Private Limited
More projects in Nagpur

Other RERA-registered projects in Nagpur

RAJ Palace Xiii
declared completion Mar 2024 · RAJ Buildcon
RAJ Palace XV
declared completion Dec 2032 · Malan Premraj Badole
Raja Bhoj Nagar
declared completion Mar 2029 · Jiyalal Sharnagat, Dilip Kawale, Daliram
Rajat Plaza
declared completion Dec 2027 · Reinforce Infra
Rajat SAI
declared completion Dec 2025 · Rajesh Girjashankar Singh
Rajatbhoomi 1
declared completion Sep 2020 · Tirupati Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Nagpur projects.

Registration last seen on RERA: 20 Oct 2026. Document and inventory dates are shown in their sections.