Pune/Project record

MahaRERA · the public record

CASSIA

BANER · BL FINE HOMES PRIVATE LIMITED

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
25 Nov 2022declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for CASSIA

MahaRERA · P52100016338

Delivery and registration

When is the project declared for completion?

CASSIA is registered with MahaRERA as P52100016338 and the promoter has declared completion for 25 Nov 2022.

25 Nov 2022

declared completion

47months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP52100016338
Registered on03 May 2018
Promoter-declared completion25 Nov 2022
Current statusCertificate Signed
Against todayabout 47 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for CASSIA record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Promoter record

What else is this promoter on record for?

BL FINE HOMES PRIVATE LIMITED is the promoter of record on 2 projects registered with MahaRERA.

2projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for CASSIA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
CASSIA1G+431 Dec 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered25 Nov 2022Due to Bad condition of approached roads of PMC Baner (time to time excavation and re construction going on for about 5 to 6 months), so that the material procedure and handling wa

Location, Land & Connectivity

Located at BANER, BANER, Haveli, Pune, 411007. Per the filed land record, the plot is bounded to the north by BY PROPERTY OF MR VINAYAK PATWARDHAN, to the south by BY INTERNAL ROAD, to the east by BY PROPERTY OF MEENA THAKKAR AND MR NIMHAN and to the west by BY PROPERTY OF MR NANAVARE. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 1 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Baner–Balewadi belt1 km
Hinjewadi Rajiv Gandhi IT Park5 km
Pune Junction / city centre12 km
Pune Int'l Airport (Lohegaon)16 km
Magarpatta / Hadapsar IT17 km
Kharadi / EON IT Park18 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Aundh

Geras Affinia
declared completion Dec 2026 · Gera Developments Private Limited
Udyam Nagari
declared completion Dec 2026 · MAP Associates
Avanti Park
declared completion Dec 2026 · Saachee Buildcon
Brain Matrix
declared completion Dec 2026 · M/s Bora Associates
Ruhi Mangalam Niyoshi
declared completion Dec 2026 · Ruhi Mangalam Associates
Sanjeevan
declared completion Dec 2026 · Badhekar & Pitale Projects LLP
More builders in Aundh

Major developers building in Aundh

More projects in Pune

Other RERA-registered projects in Pune

Castel Royale Tower Nine
declared completion Sep 2029 · Avinash Bhosale Group
Castle Gate A Wing
declared completion Dec 2027 · Ravikumar Ambalal Shah
Castle Gate B Wing
declared completion Dec 2028 · Ravikumar Ambalal Shah
Castle Hills
declared completion Dec 2027 · Prarabdha Associates LLP
Casuarina - Cluster C AND D
declared completion Dec 2028 · Gangotree Homes & Holidays
Casuarina - Country Homes
declared completion Dec 2029 · Gangotree Homes AND Holidays

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Pune projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.