0units filed as unsoldInventory · 25 October 2026
24 Mar 2025declared completionMahaRERA registration · read 19 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 19 Jul 2026

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗

Free project details

Registration read 19 Jul 2026

RERA details for KESHAR RESIDENCY

MahaRERA · P52100052987

Delivery and registration

When is the project declared for completion?

KESHAR RESIDENCY is registered with MahaRERA as P52100052987 and the promoter has declared completion for 24 Mar 2025.

24 Mar 2025

declared completion

19months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 19 Jul 2026

MahaRERA registrationP52100052987
Registered on10 Oct 2023
Promoter-declared completion24 Mar 2025
Current statusCertificate Signed
Against todayabout 19 months past the declared date

What the filings record, unit by unit

Read from MahaRERA on 25 October 2026

MahaRERA publishes, unit by unit, what this promoter filed: which units are sold and which are not, the RERA carpet area of each, and for sold or booked entries the filed agreement value — the consideration filed for that specific unit. On this project 12 units carry one, and Every unit on the filing is recorded sold or booked.

A filed consideration is the amount the promoter reported for one unit. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the unit is available to you today. Only one observation of this ledger so far: no change can be reported yet.

This snapshot marks all units in KESHAR RESIDENCY as sold or booked. It does not establish current availability. The filed values can still help you compare a quote. The Sales Report lists the 12 sold or booked entries with filed values: each unit, its carpet area, the consideration filed against it and the rate that works out to. Built from the filing itself, sent by email.

See all 12 filed sold/booked entries — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
KESHAR RESIDENCY1G+4-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered24 Mar 2025Due to time delay getting the labour issue & financial problem there for we are not able to complete the project on committed dated as mentioned in RERA i.e. 24/12/2024

Location, Land & Connectivity

Located at DEHUGAON, DEHU-ALANDI ROAD, Haveli, Pune, 412109. Per the filed land record, the plot is bounded to the north by SR NO-51, to the south by ROAD, to the east by SR NO-55 and to the west by SR NO-55. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dehu

Gathagram Sector 2
declared completion Nov 2026 · Harit Landmarks LLP
Gathagram Sector 4 Phase 1
declared completion Nov 2026 · Harit Landmarks LLP
Gathagram Sector 5 Phase 1
declared completion Nov 2026 · Harit Landmarks LLP
Dwarkadheesh Residency
Not filing quarterly progress reports · declared completion Dec 2026 · Harichandra Rambhau Satav
JDS Residency
declared completion Dec 2026 · J D S Group
Ovitirth
declared completion Dec 2026 · Royal Land Developers
More projects in Pune

Other RERA-registered projects in Pune

Keshav Kunj
declared completion Dec 2025 · M/S Sanskruti Developers AND Builders
Keshav Kunj
declared completion Dec 2027 · Graystone Realty
Keshavbaag
declared completion Dec 2022 · Shlok Enterprises
Keshavyog Residency
declared completion Dec 2026 · Siddhivinayak Builders
Ketan Heights Chsl
declared completion Dec 2026 · Kotibhaskar Infrastructures &develop
Ketan Heights Wing / Building No A
declared completion Dec 2026 · Ketandevelopers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Pune projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.