Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
03 Jan 2025declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for More Nivas

MahaRERA · P52100052024

Delivery and registration

When is the project declared for completion?

More Nivas is registered with MahaRERA as P52100052024 and the promoter has declared completion for 03 Jan 2025.

03 Jan 2025

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP52100052024
Registered on19 Jul 2023
Promoter-declared completion03 Jan 2025
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for More Nivas record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Deregistered — MahaRERA has deregistered this project — it is off the register.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for More Nivas in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
More Nivas1G+403 Jan 2025

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Bhor, More Ali, Bhor, Pune, 412206. Per the filed land record, the plot is bounded to the north by Common Road, to the south by Property of C S No 1288 and 1284, to the east by Property of C S No 1277 and to the west by Common Property of C S No 1275. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bhor

Prospera County
declared completion Oct 2026 · Mudraa Life Spaces PVT LTD
Aarya Green County
declared completion Dec 2027 · Nirmitee Developers
Marigolds Valley
declared completion Dec 2027 · Castle Dream Space
Swapnalok Nagari, Bhor, Building NO. 4
Deregistered by MahaRERA · declared completion Dec 2027 · Swapnalok Developers
Villament
declared completion Dec 2027 · Gangotree Homes AND Holidays
Samara Hills
declared completion Jun 2028 · Paranjape Schemes LTD
More builders in Bhor

Major developers building in Bhor

More projects in Pune

Other RERA-registered projects in Pune

Morella
declared completion Dec 2023 · Global Properties
Morella Phase II
declared completion Dec 2026 · Buchade Patil Developers
Moreshwar Enclave
declared completion Dec 2026 · Moreshwar Developers
Moreshwar Residency
declared completion Sep 2024 · S K Developers
Morya Alphanso
declared completion Jun 2023 · Morya Developers
Morya Apartment
declared completion Jun 2024 · JAY Sadguru Builders & Developers

What to verify (inactive registration)

  1. Download the MahaRERA order stating the reason for deregistration or suspension — this is public on the portal.
  2. Check whether the developer has filed a challenge in the Appellate Tribunal and whether the order is stayed.
  3. Do not make any further payments until the registration status is restored or you obtain legal advice.
  4. Contact MahaRERA's helpdesk for guidance on alternative arrangements or pending dues.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Pune projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.