Pune/Project record

MahaRERA · the public record

NAVJYOT ABHA PHASE I

Pune · SUMERU BUILDCON PRIVATE LIMITED

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Dec 2023declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for NAVJYOT ABHA PHASE I

MahaRERA · P52100011535

Delivery and registration

When is the project declared for completion?

NAVJYOT ABHA PHASE I is registered with MahaRERA as P52100011535 and the promoter has declared completion for 30 Dec 2023.

30 Dec 2023

declared completion

34months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP52100011535
Registered on31 Aug 2017
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 34 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for NAVJYOT ABHA PHASE I record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Promoter record

What else is this promoter on record for?

SUMERU BUILDCON PRIVATE LIMITED is the promoter of record on 2 projects registered with MahaRERA.

2projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for NAVJYOT ABHA PHASE I in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
C1G+13-
D1G+13-

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for NAVJYOT ABHA PHASE I, with orders passed in 0 of them.

2complaints

0with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC1240044317/10/2024Jaydeep padmakar pathakji vs SUMERU BUILDCON PRIVATE LIMITEDpending / no order on file
CC1250383701/11/2025Subramanyam Vilas Ghante vs SUMERU BUILDCON PRIVATE LIMITEDpending / no order on file

Location, Land & Connectivity

Located at Haveli, Pune, 411041. Per the filed land record, the plot is bounded to the north by SURVEY NO 149, to the south by PROPERTYOF VAISHNAVI PROMOTERS AND BUILDERS, to the east by REMAINING PART OF S NO 150-1 AND S NO 150-3 and to the west by REMAINING PLOT ARE AT SURVEY NO 150-1. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 117 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park117 km
Baner–Balewadi belt123 km
Pune Junction / city centre133 km
Pune Int'l Airport (Lohegaon)134 km
Kharadi / EON IT Park137 km
Magarpatta / Hadapsar IT138 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dhayari

Homedale
declared completion Dec 2026 · M/s. Om Shiv Sai Promoters & Develop
Navjyot Abha Phase II B And D
Not filing quarterly progress reports · declared completion Dec 2026 · Sumeru Buildcon Private Limited
Shriniwas Greenland County Phase II
Not filing quarterly progress reports · declared completion Dec 2026 · Darode JOG Dangat Venture
Anvi Business Park
declared completion Dec 2026 · G K Group
Arunika A,B Wing
Not filing quarterly progress reports · declared completion Dec 2026 · Dhareshwar Buildcon
Bhidewadi
declared completion Dec 2026 · Bhide & Bhadane Realties
More builders in Dhayari

Major developers building in Dhayari

More projects in Pune

Other RERA-registered projects in Pune

Navjyot Abha Phase II B And D
declared completion Dec 2026 · Sumeru Buildcon Private Limited
Navkaar Heights
declared completion Dec 2024 · Navkaar NX Developers LLP
Navkar A Building
declared completion Jun 2019 · Majestique Lifespaces LLP
Navkar Anand
declared completion Aug 2025 · Four Pillars
Navkar Park
declared completion Dec 2019 · Parkons Trendz
Navkar Park
declared completion Mar 2023 · Himalaya Landmarks Private Limited

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Pune projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.