Pune/Project record

MahaRERA · the public record

PADMANABH GOLDEN VALLEY PHASE-I BUILDING B AND C

DHAYARI · OM BALAJI PLAZA

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Oct 2020declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for PADMANABH GOLDEN VALLEY PHASE-I BUILDING B AND C

MahaRERA · P52100001995

Delivery and registration

When is the project declared for completion?

PADMANABH GOLDEN VALLEY PHASE-I BUILDING B AND C is registered with MahaRERA as P52100001995 and the promoter has declared completion for 30 Oct 2020.

30 Oct 2020

declared completion

72months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP52100001995
Registered on31 Jul 2017
Promoter-declared completion30 Oct 2020
Current statusCertificate Signed
Against todayabout 72 months past the declared date

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for PADMANABH GOLDEN VALLEY PHASE-I BUILDING B AND C in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
BUILDING B1G+13-
BUILDING C1G+13-

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for PADMANABH GOLDEN VALLEY PHASE-I BUILDING B AND C, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000002327225/07/2019HEMCHANDRA RAJARAM BHONSALE vs VISHNU NARAYAN HARIHAR THROUGH OM BLALJI PLAZAorder passed

Legal & Litigation

The promoter has declared 2 court cases on this project to MahaRERA. Filed descriptions (status fields empty): 1 “MATTER IS DISPOSED OFF AND IN FAVOUR OF OM BALAJI PLAZA”; 1 “ORDER PASSED BY HONOURABLE COURT THAT SAID DISPUTE IS NOT IN RESPECT OF JOINT VENTURE AGREEMENT BETW”. These are the promoter's filed statements, not a current court check. A disposed application or motion does not establish that the whole case is closed. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your unit. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
V S Malkalpatte Reddy Fifth Jt Civil Judge Senior Division Pune712/20152015Status not supplied
Filed description: MATTER IS DISPOSED OFF AND IN FAVOUR OF OM BALAJI PLAZA
V S Malkalpatte Reddy Fifth Jt Civil Judge Senior Division Pune1044/20152015Status not supplied
Filed description: ORDER PASSED BY HONOURABLE COURT THAT SAID DISPUTE IS NOT IN RESPECT OF JOINT VENTURE AGREEMENT BETW

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Apr 20201. We have applied for the Site Elevation NOC (project requirement) as on 18/09/2019(copy of the application attached), we will receive this NOC up to March-April 2020. 2. As soon

Location, Land & Connectivity

Located at DHAYARI, SINHGAD ROAD, Pune City, Pune, 411041. Per the filed land record, the plot is bounded to the north by BY SURVEY NO 147-9 DHAYARI, to the south by SURVEY NO 147-14 AND 16 DHAYARI, to the east by BY ROAD and to the west by LAND BELONGING TO CHAKANKAR. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 12 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Pune Junction / city centre11 km
Baner–Balewadi belt12 km
Magarpatta / Hadapsar IT14 km
Hinjewadi Rajiv Gandhi IT Park17 km
Kharadi / EON IT Park17 km
Pune Int'l Airport (Lohegaon)18 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dhayari

Homedale
declared completion Dec 2026 · M/s. Om Shiv Sai Promoters & Develop
Navjyot Abha Phase II B And D
Not filing quarterly progress reports · declared completion Dec 2026 · Sumeru Buildcon Private Limited
Shriniwas Greenland County Phase II
Not filing quarterly progress reports · declared completion Dec 2026 · Darode JOG Dangat Venture
Anvi Business Park
declared completion Dec 2026 · G K Group
Arunika A,B Wing
Not filing quarterly progress reports · declared completion Dec 2026 · Dhareshwar Buildcon
Bhidewadi
declared completion Dec 2026 · Bhide & Bhadane Realties
More builders in Dhayari

Major developers building in Dhayari

More projects in Pune

Other RERA-registered projects in Pune

Padmanabh Phase 1
declared completion Sep 2022 · Khushanai Developers
Padmanabh Phase II
declared completion Dec 2021 · Darode JOG Homes PVT LTD
Padmarang
declared completion Mar 2027 · SBS Prroperties
Padmashree Phase - I
declared completion Dec 2027 · Nilesh Shashikant Ostwal
Padmavati Angan
declared completion Mar 2027 · Samarth Construction & Developers
Padmavati Avenue
declared completion Dec 2027 · Jawalkar Realties

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Pune projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.