Pune/Project record

MahaRERA · the public record

SANGAMESHWARI

SINHAGAD ROAD · SHREE OMKAR DEVELOPERS / SUMANGAL ASSOCIATES

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
31 Dec 2023declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for SANGAMESHWARI

MahaRERA · P52100011128

Delivery and registration

When is the project declared for completion?

SANGAMESHWARI is registered with MahaRERA as P52100011128 and the promoter has declared completion for 31 Dec 2023.

31 Dec 2023

declared completion

34months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP52100011128
Registered on31 Aug 2017
Promoter-declared completion31 Dec 2023
Current statusCertificate Signed
Against todayabout 34 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SANGAMESHWARI record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SANGAMESHWARI in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
SANGAMESHWARI1G+1330 Mar 2021
SANGAMESHWARI B1G+530 Mar 2021

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for SANGAMESHWARI, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000029018922/01/2024Hemantkumar Vasantrao Jagtap vs Shree Omkar Developers andSumangal Associates Through its PartnerShri. Sanjay D Dapodikarorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Mar 2022DUE TO LOCKDOWN AND DELAY IN MATERIAL SUPPLY 1 YEAR EXTENSION IS REQUIRED
30 Mar 202231 Dec 2023there was material shortage issue and also due lockdown entire work was delayed

Location, Land & Connectivity

Located at SINHAGAD ROAD, SINHAGAD ROAD, Haveli, Pune, 411030. Per the filed land record, the plot is bounded to the north by SARITA NAGARI PHASE, to the south by ROAD, to the east by PLOT NO 37 and to the west by PLOT NO 35. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 9 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Pune Junction / city centre6 km
Baner–Balewadi belt9 km
Magarpatta / Hadapsar IT10 km
Kharadi / EON IT Park13 km
Pune Int'l Airport (Lohegaon)13 km
Hinjewadi Rajiv Gandhi IT Park15 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Sadashiv Peth

SAI - Lalitha
declared completion Dec 2026 · Sairam Developers
9 Sadashiv C Building
declared completion Dec 2026 · Pinnacle Neostar Corporation Pvt. Ltd.
Sadashiv Vishnu
Not filing quarterly progress reports · declared completion Dec 2026 · Sadashiv Vishnu Realty LLP
Enjays Paramount
declared completion Dec 2026 · Enjay Infra
Kulkarni Wada
declared completion Dec 2026 · Jagdish Universal Superbiz Developers An
Vardhishnu
declared completion Dec 2026 · Vishwam
More builders in Sadashiv Peth

Major developers building in Sadashiv Peth

More projects in Pune

Other RERA-registered projects in Pune

Sangeetdhara
declared completion Dec 2025 · Vishva Gangotree Buildcon
Sangharsa Apartment Building F
declared completion Dec 2029 · Not Available
Sanghavi Paradise A Building
declared completion Jul 2024 · Sanjay Walchand Sanghavi
Sanghavi Paradise B And C Building
declared completion Jul 2018 · Sanjay Walchand Sanghavi
Sanghvi Premio
declared completion Oct 2026 · Nitin Kantilal Sanghvi
Sanidhya Residency
declared completion Jun 2021 · Prestige Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Pune projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.