Shillim Residences - Phase 1

Shilimb Village · Writer Lifestyle Pvt. Ltd.

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
12 Dec 2019declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for Shillim Residences - Phase 1

MahaRERA · P52100015159

Delivery and registration

When is the project declared for completion?

Shillim Residences - Phase 1 is registered with MahaRERA as P52100015159 and the promoter has declared completion for 12 Dec 2019.

12 Dec 2019

declared completion

82months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP52100015159
Registered on02 Feb 2018
Promoter-declared completion12 Dec 2019
Current statusCertificate Signed
Against todayabout 82 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Shillim Residences - Phase 1 record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Shillim Residences - Phase 1 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+0.

BuildingWingsFloorsDeclared completion
Villa Number 121G+012 Dec 2019
Villa Number 131G+012 Dec 2019
Villa Number 141G+012 Dec 2019
Villa Number 151G+012 Dec 2019
Villa Number 161G+012 Dec 2019
Villa Number 111G+012 Dec 2019
Villa Number 101G+012 Dec 2019
Villa Number 81G+012 Dec 2019
Villa Number 71G+012 Dec 2019
Villa Number 61G+012 Dec 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Shilimb Village, Javan Tungi Road, Mawal, Pune, 410406. Per the filed land record, the plot is bounded to the north by Village Chawsar, to the south by Village Vagheshwar, to the east by Village Shiravli and to the west by Shilimb of village Shilimb. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 30 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park30 km
Baner–Balewadi belt35 km
Pune Junction / city centre46 km
Pune Int'l Airport (Lohegaon)50 km
Magarpatta / Hadapsar IT52 km
Kharadi / EON IT Park52 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Done

Blue Oak
declared completion Jun 2027 · Regal Era Landmarks
The Purrple County - Studio A1
declared completion Dec 2027 · Khemlani Constructions
Paloma - Eva
declared completion Sep 2025 · Synergy Properties
More projects in Pune

Other RERA-registered projects in Pune

Shilp Shantivan
declared completion Jun 2028 · Echo Stone Buildcon
Shilpa - II
declared completion Oct 2026 · Swojas Icon Properties LLP
Shilpashree
declared completion Jun 2028 · Parulekar Landmarks LLP
Shinde Associates
declared completion Mar 2027 · Anil Jagannath Shinde
Shinde Heights
declared completion Mar 2023 · Jadhav Developers
Shinde Park
declared completion Aug 2018 · Krishnarav Ganapatarav Ghadge

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Pune projects.