Pune/Project record

MahaRERA · the public record

SIGMA CENTURIA

papde wasti · Sigma Realtors

Project Review · example purchase

Spending a few crores on a home? ₹4,999 to check what you’re buying.

Check what the plans put beside your home, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

0units filed as unsoldInventory · 18 October 2026
13 Jun 2025declared completionMahaRERA registration · read 18 Jul 2026
70registered unitsMahaRERA registration · read 18 Jul 2026

From another project · Life Republic Atmos Phase II

Avoid bad decisions, only go for the best homes.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
Life Republic Atmos Phase II Project Review · first page
First page of the complete sample.

Free project details

Registration read 18 Jul 2026

RERA details for SIGMA CENTURIA

MahaRERA · P52100003501

Delivery and registration

When is the project declared for completion?

SIGMA CENTURIA is registered with MahaRERA as P52100003501 and the promoter has declared completion for 13 Jun 2025.

13 Jun 2025

declared completion

16months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP52100003501
Registered on05 Aug 2017
Promoter-declared completion13 Jun 2025
Current statusCertificate Signed
Against todayabout 16 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SIGMA CENTURIA record 1 quarterly progress report since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

  • Filing progress reports — 1 quarterly progress report on record since registration, with no current default.

Construction

How much construction cost has been reported?

In SIGMA CENTURIA, ₹9.87 Cr of a declared ₹9.88 Cr estimated project cost is reported as incurred, about 99.9%, as at the last certified filing with MahaRERA.

99.9%

₹9.87 Cr

of ₹9.88 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 18 Jul 2026

Sales

How many are filed as sold or booked?

In SIGMA CENTURIA, 47 of 47 homes filed with MahaRERA are recorded as sold or booked, about 100%, and 0 are filed as unsold.

100%sold or booked

47 of 47 homes

₹15.82 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹15.82 Cr (about 100%) is recorded as collected and ₹0 as receivable. The registration lists 70 homes; this inventory lists 47. These are separate filed records. Their counts do not match; neither count establishes today's availability.

Source · MahaRERA sold/unsold inventory filing · read 18 Jul 2026

Filed agreement values: across 47 sold or booked entries with usable filed values and areas, the effective carpet rate is ₹7,651/sqft, with eight in ten falling between ₹5,618 and ₹8,511 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The inventory filing also declares: 23 owner/investor-held.

What the filings record, home by home

Read from MahaRERA on 18 October 2026

This unit list contains 70 entries; the separate sales summary contains 47. The lists can differ in status coverage and filing date. Use the source date shown with each.

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for sold or booked entries the filed agreement value — the consideration filed for that specific home. On this project 47 homes carry one, and Every home on the filing is recorded sold or booked.

A filed consideration is the amount the promoter reported for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

This snapshot marks all homes in SIGMA CENTURIA as sold or booked. It does not establish current availability. The filed values can still help you compare a quote. The Sales Report lists the 47 sold or booked entries with filed values: each home, its carpet area, the consideration filed against it and the rate that works out to. Built from the filing itself, sent by email.

See all 47 filed sold/booked entries — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7 and 70 homes are registered across the project.

BuildingWingsFloorsUnitsDeclared completion
SIGMA CENTURIA RESIDENTIAL1G+770-
SIGMA CENTURIA COMMERCIAL1---

Unit mix on the filing: 70 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 4 times, as recorded on the register.

FromExtended toStated reason
as registered30 Sep 2019due to change of sanctioning authority from PMRDA to PMC, we got delayed for water & garden noc required for final completion. we got part occupancy certificate (o.c.c/0664/18) dat
30 Sep 201930 Sep 2021Respected Authority, We obtained part occupancy certificate( O.C.C/0664/18 PMC) for sigma centuria phase 1. i.e 60 units out of 70 units EXT52100000703. Now, we are planning to a
30 Sep 202130 Dec 20221] Delay in process of Amenity hand over. 2] Proposing revision in lay out. 3] out of 70 units , 60 unit got part occupancy certificate. only 10 units & club house are remaining.
30 Dec 202213 Jun 2025we have obtained full occupancy certificate from Fursungi-Uruli Devachi Municipal Council dated 13/06/2025.

Location, Land & Connectivity

Located at papde wasti, sr no 204/4/5/6/7, Haveli, Pune, 412308. Per the filed land record, the plot is bounded to the north by 12 M ROAD, to the south by HISSA NO 9, to the east by BALANCE 204 and to the west by HISSA NO 8. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 4 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Magarpatta / Hadapsar IT4 km
Kharadi / EON IT Park8 km
Pune Junction / city centre9 km
Pune Int'l Airport (Lohegaon)11 km
Baner–Balewadi belt20 km
Hinjewadi Rajiv Gandhi IT Park25 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Fursungi

Green Hive Plus Wing A4
declared completion Dec 2026 · Ram India Shelters
THE Mpire Building E
declared completion Dec 2026 · AGN Venture
Vandan Vihar
declared completion Jun 2027 · GVN Developers PVT LTD
AGS Complex
declared completion Sep 2027 · AGS Properties
Pacific Tower
declared completion Sep 2027 · Chaitanya Developers
Evara
declared completion Dec 2027 · G D Developers
More builders in Fursungi

Major developers building in Fursungi

More projects in Pune

Other RERA-registered projects in Pune

Sigma Centuria Phase II
declared completion Dec 2030 · Sigma2 Buildzone LLP
Sigma One Bizbay
declared completion Mar 2027 · Free Bird Developers LLP
Sigma ONE Grandstand
declared completion Dec 2021 · Sigma ONE Venture Previously Sigma ONE K
Signature
declared completion Apr 2028 · Vaishali Pravin Bafna
Signature Business Centre
declared completion Dec 2027 · Signature Landmarks LLP
Signature Corner
declared completion Mar 2028 · Adarsh Associates & Developer

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Pune projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.