Pune/Project record

MahaRERA · the public record

SWASTIK PEARL

TALEGAON DABHADE · SWASTIK BUILDERS

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Nov 2024declared completionMahaRERA registration · read 19 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 19 Jul 2026

Free project details

Registration read 19 Jul 2026

RERA details for SWASTIK PEARL

MahaRERA · P52100027178

Delivery and registration

When is the project declared for completion?

SWASTIK PEARL is registered with MahaRERA as P52100027178 and the promoter has declared completion for 30 Nov 2024.

30 Nov 2024

declared completion

23months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 19 Jul 2026

MahaRERA registrationP52100027178
Registered on20 Nov 2020
Promoter-declared completion30 Nov 2024
Current statusCertificate Signed
Against todayabout 23 months past the declared date

Promoter record

What else is this promoter on record for?

SWASTIK BUILDERS is the promoter of record on 3 projects registered with MahaRERA.

3projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 19 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SWASTIK PEARL in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 19 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
SWASTIK PEARL1G+4-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2023We apply for extension of the following project Swastik Pearl registered with the regulatory authority vide project registration certificate bearing no. P52100027178 which expires
30 Dec 202331 Jul 2024We, hereby apply for extension u/s 7(3) of the registered project bearing vide no. P52100027178 up to 31/07/2024. As prescribed under circular no 07/2019 dated 8 Feb 2019, the cons
31 Jul 202430 Nov 2024We, hereby apply for extension u/s 7(3) of the registered project bearing vide no. P52100027178 up to 30/11/2024. As prescribed under circular no 07/2019 dated 8 Feb

Location, Land & Connectivity

Located at TALEGAON DABHADE, LAXMIBAG COLONY, Mawal, Pune, 410506. Per the filed land record, the plot is bounded to the north by 9 MTR ROAD, to the south by PLOT NO 36, to the east by OPEN LAND and to the west by 9 MTR ROAD. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Talegaon Dabhade

Vaarivana Phase D - 2A
declared completion Oct 2026 · Sanjivani Integrated Township LLP
Rohan Anand Phase II
declared completion Dec 2026 · Rohan Builders & Developers Private
Abhimaan Homes Phase 3
declared completion Dec 2026 · Rising Propcon LLP
City Plaza
Past its declared completion date · declared completion Dec 2026 · Shreenathji Construction LLP
Cradle OF Life Phase 1
declared completion Dec 2026 · Gadsing Infra & Hospitality LLP
Greenville
declared completion Dec 2026 · Shreeji Developers
More builders in Talegaon Dabhade

Major developers building in Talegaon Dabhade

More projects in Pune

Other RERA-registered projects in Pune

Swastik Samruddhi
declared completion Dec 2022 · Swastik Associates
Swastik Sanskruti
declared completion Dec 2022 · Swastik Developers
Swastik Twin Tower
declared completion Jul 2026 · Swastik Builders
Swastik Vyom
declared completion Mar 2027 · Swastik Venture
Swastika
declared completion Dec 2026 · Vikram RAM Agarwal
Swastishree
declared completion Jun 2024 · Swastik Homes

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Pune projects.

Registration last seen on RERA: 11 Sep 2026. Document and inventory dates are shown in their sections.