SWAYAMPRABHA

Rambaug Colony · Gruha Navnirman Developers

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
15 Aug 2019declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for SWAYAMPRABHA

MahaRERA · P52100001118

Delivery and registration

When is the project declared for completion?

SWAYAMPRABHA is registered with MahaRERA as P52100001118 and the promoter has declared completion for 15 Aug 2019.

15 Aug 2019

declared completion

86months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP52100001118
Registered on26 Jul 2017
Promoter-declared completion15 Aug 2019
Current statusCertificate Signed
Against todayabout 86 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SWAYAMPRABHA record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Promoter record

What else is this promoter on record for?

Gruha Navnirman Developers is the promoter of record on 5 projects registered with MahaRERA.

5projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SWAYAMPRABHA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+10.

BuildingWingsFloorsDeclared completion
SWAYAMPRBHA1G+10-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered15 Aug 2019We hereby request for extension again due to following reasons. Part Completion was received from PMC on date 16/05/2018 Due to various compliance related issues at society end a
15 Aug 201915 Aug 2019We hereby request for extension of 4 months in order to finish the site which is more than 80% complete. Kindly find below few major reasons for delay: 1. The last commencement

Location, Land & Connectivity

Located at Rambaug Colony, Rambaug Colony, Pune City, Pune, 411030. Per the filed land record, the plot is bounded to the north by PMC ROAD, to the south by PLOT NO 13, to the east by PLOT NO 30 and to the west by PLOT NO 28. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 7 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Pune Junction / city centre3 km
Magarpatta / Hadapsar IT7 km
Kharadi / EON IT Park10 km
Baner–Balewadi belt11 km
Pune Int'l Airport (Lohegaon)11 km
Hinjewadi Rajiv Gandhi IT Park16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Sadashiv Peth

SAI - Lalitha
declared completion Dec 2026 · Sairam Developers
9 Sadashiv C Building
declared completion Dec 2026 · Pinnacle Neostar Corporation Pvt. Ltd.
Sadashiv Vishnu
Not filing quarterly progress reports · declared completion Dec 2026 · Sadashiv Vishnu Realty LLP
Enjays Paramount
declared completion Dec 2026 · Enjay Infra
Kulkarni Wada
declared completion Dec 2026 · Jagdish Universal Superbiz Developers An
Vardhishnu
declared completion Dec 2026 · Vishwam
More builders in Sadashiv Peth

Major developers building in Sadashiv Peth

More projects in Pune

Other RERA-registered projects in Pune

Sweet Home CO-Operative Housing Society
declared completion Mar 2027 · Ashwamedh Spaces Private Limited
Sweet Home Pmay
declared completion May 2025 · Deshmukh Developments
Swiss Plaza
declared completion Mar 2019 · Moti Udharam Panjabi
Swojas Aasara
declared completion Sep 2028 · Swojas United Constructions LLP
Swojas Advait
declared completion Apr 2026 · Swojas Realtors LLP
Swojas Avani
declared completion Jun 2025 · Swojas Realtors LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.