VNS Nirmaan Infra

Malegaon Bk · VNS NIRMAAN INFRA

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Jul 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Jul 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100019592

Delivery and registration

When is the project declared for completion?

VNS Nirmaan Infra is registered with MahaRERA as P52100019592 and the promoter has declared completion for 31 Jul 2023.

31 Jul 2023

declared completion

38months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100019592
Registered on12 Feb 2019
Promoter-declared completion31 Jul 2023
Current statusCertificate Signed
Against todayabout 38 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for VNS Nirmaan Infra record 19 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 19 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Vns Nirmaan Infra is the promoter of record on 33 projects registered with MahaRERA, 4 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

33projects

registered with MahaRERA

4flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for VNS Nirmaan Infra in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+2.

BuildingWingsFloorsDeclared completion
Amenity Space Plot No 21G+231 Jul 2022
Amenity Space Plot No 31G+231 Jul 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Waqf Trabunal Aurangabad902019Due To Supreme Court Status Quo Order No Construction Shall Be Effected Nor Any Third Party Rights

Location, Land & Connectivity

Located at Malegaon Bk, Zail singh Road, Pune City, Pune, 413115. Per the filed land record, the plot is bounded to the north by Amenity Plot No 4, to the south by Amenity No 1, to the east by 12 Mtr Road and to the west by Gat 230 H 5 remaing part. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Malegaon Bk

Shripal Park
Not filing quarterly progress reports · possession by Mar 2027 · Shripal Landmarks AOP
Ramraj Residency
possession by Dec 2028 · Ramchandra Dinkar Devkate
Shri Bhavani Market
Not filing quarterly progress reports · possession by Apr 2029 · Shri Bhavani Shankar Developers
Ramraj Residency B Building
possession by Dec 2030 · Ramchandra Dinkar Devkate
Anandwan Apartment
Not filing quarterly progress reports · declared completion Dec 2025 · Rudransh Infra
Avadhut Residency Phase II
declared completion Jun 2022 · Yogesh Balasaheb Taware

Other RERA-registered projects in Pune

Vnsvl Shubh Infinity
declared completion Dec 2025 · Viman Nagar Shubh Ventures LLP
Vnsvl Shubh Nirvana Phase 1
declared completion Dec 2025 · Viman Nagar Shubh Ventures LLP
Vnsvl Shubh Nirvana - Phase II
declared completion Jun 2026 · Viman Nagar Shubh Ventures LLP
Vnsvl Shubh Nirvana Phase III
possession by Dec 2026 · Viman Nagar Shubh Ventures LLP
Vnsvl Shubh Nirvana Phase IV
possession by Jun 2027 · Viman Nagar Shubh Ventures LLP
Vogue 25
possession by Oct 2026 · Goodbrick Realty Private Limited

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 15 Sep 2026