MahaRERA · the public record
VNS Nirmaan Infra
Malegaon Bk · VNS NIRMAAN INFRA
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
31 Jul 2023
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P52100019592
Delivery and registration
When is the project declared for completion?
VNS Nirmaan Infra is registered with MahaRERA as P52100019592 and the promoter has declared completion for 31 Jul 2023.
31 Jul 2023
declared completion
38months past
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P52100019592 |
| Registered on | 12 Feb 2019 |
| Promoter-declared completion | 31 Jul 2023 |
| Current status | Certificate Signed |
| Against today | about 38 months past the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for VNS Nirmaan Infra record 19 quarterly progress reports since registration.
19quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Completion date lapsed — the registered completion date has lapsed without a recorded finish.
- Filing progress reports — 19 quarterly progress reports on record since registration, with no current default.
Promoter record
What else is this promoter on record for?
Vns Nirmaan Infra is the promoter of record on 33 projects registered with MahaRERA, 4 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).
33projects
registered with MahaRERA
4flagged
by MahaRERA
Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.
Source · MahaRERA register, all projects · read 12 Jul 2026
Sales
Are registered sale-agreement prices available?
No registered sale-agreement price is recorded for VNS Nirmaan Infra in the MahaRERA project file.
Not available
This is what the record does not contain, not a value of zero.
Source · MahaRERA project file · checked 12 Jul 2026
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+2.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| Amenity Space Plot No 2 | 1 | G+2 | 31 Jul 2022 |
| Amenity Space Plot No 3 | 1 | G+2 | 31 Jul 2022 |
Complaints
No buyer complaints were on this project's MahaRERA record at the time of reading.
Legal & Litigation
The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.
| Court | Case no. | Year | Status |
|---|---|---|---|
| Waqf Trabunal Aurangabad | 90 | 2019 | Due To Supreme Court Status Quo Order No Construction Shall Be Effected Nor Any Third Party Rights |
Location, Land & Connectivity
Located at Malegaon Bk, Zail singh Road, Pune City, Pune, 413115. Per the filed land record, the plot is bounded to the north by Amenity Plot No 4, to the south by Amenity No 1, to the east by 12 Mtr Road and to the west by Gat 230 H 5 remaing part. These are the boundaries as recorded in the filed land record.