Pune/Project record

MahaRERA · the public record

WINDCHIME HOMES PHASE 3

SOMATANE · SUJAY VENTURES

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
31 Dec 2024declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for WINDCHIME HOMES PHASE 3

MahaRERA · P52100045681

Delivery and registration

When is the project declared for completion?

WINDCHIME HOMES PHASE 3 is registered with MahaRERA as P52100045681 and the promoter has declared completion for 31 Dec 2024.

31 Dec 2024

declared completion

22months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP52100045681
Registered on06 Jun 2022
Promoter-declared completion31 Dec 2024
Current statusCertificate Signed
Against todayabout 22 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for WINDCHIME HOMES PHASE 3 record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Promoter record

What else is this promoter on record for?

SUJAY VENTURES is the promoter of record on 2 projects registered with MahaRERA.

2projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for WINDCHIME HOMES PHASE 3 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
B21G+731 Dec 2024

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at SOMATANE, SHIRGAONSAI MANDIR ROAD, Mawal, Pune, 410506. Per the filed land record, the plot is bounded to the north by GAT NO 258, to the south by INTERNAL 12 METER WIDE ROAD, to the east by BUILDING B1 WINDCHIME HOMES PHASE 1 and to the west by BUILDING D2 WINDCHIME HOMES PHASE 2. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Talegaon Dabhade

Vaarivana Phase D - 2A
declared completion Oct 2026 · Sanjivani Integrated Township LLP
Rohan Anand Phase II
declared completion Dec 2026 · Rohan Builders & Developers Private
Abhimaan Homes Phase 3
declared completion Dec 2026 · Rising Propcon LLP
City Plaza
Past its declared completion date · declared completion Dec 2026 · Shreenathji Construction LLP
Cradle OF Life Phase 1
declared completion Dec 2026 · Gadsing Infra & Hospitality LLP
Greenville
declared completion Dec 2026 · Shreeji Developers
More builders in Talegaon Dabhade

Major developers building in Talegaon Dabhade

More projects in Pune

Other RERA-registered projects in Pune

Windermere Phase 1
declared completion Dec 2018 · Vascon Engineers Ltd
Windermere Phase 2
declared completion Mar 2019 · Vascon Engineers Ltd
Window Cooperative Housing Society Limited 131/1
declared completion Jul 2026 · Windows Co-Operative Housing Society Ltd
Window Cooperative Housing Society Limited 222/2
declared completion Dec 2026 · Windows Co-Operative Housing Society Ltd
Winds OF JOY Project A
declared completion Nov 2028 · Pegasus Properties Pvt. Ltd.
Winds OF JOY Project B
declared completion Oct 2028 · Pegasus Properties Pvt. Ltd.

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Pune projects.

Registration last seen on RERA: 11 Sep 2026. Document and inventory dates are shown in their sections.