RERA Property Intelligence Report · Preview

DNR Arista Phase 2

INESA VENTURES · Bengaluru East · K-RERA PRM/KA/RERA/1251/446/PR/240306/006662

Report coverage

K-RERA registry & builder-record report

What this report covers

  • Official K-RERA registry facts — units, cost, land area, towers, approvals
  • Complaint / litigation & compliance history
  • Builder delivery record across their K-RERA portfolio
  • Construction trajectory & sales pace from quarterly filings

To confirm directly with the builder

  • No dimensioned unit layouts could be confidently extracted from the filed plans.
Not yet
Completion certificate
None declared
Legal status
Other RERA projects by builder

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk rating, the specific red-flag findings, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the builder before you commit.

Unlock in the ₹999 report →

132
Registered units
₹107.0 Cr
Est. construction cost
Units profiled
46
RERA documents on file

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units132Total inventory registered with K-RERA.
Official carpet area2,448 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Registered land area17,705 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI3.08Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered towers/wings1Official tower/wing count in the K-RERA detail page.
Parking disclosed143 total (0 open) — 1.08 spaces/unitConfirm whether your quoted unit includes an allotted parking space and where it sits.
Project start date19-03-2012

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
4BHK12100%2,448 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Tower 312132143-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 132 official flat/unit rows, matching the 132 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3BHK108104.0-106.0 sqm455.8-461.2 sqm108
2BHK1380.5 sqm344.9 sqm13
4BHK11130.0 sqm554.3 sqm22

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Tower 313280.5-130.0 sqm344.9-554.3 sqm143
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
F-0101Tower 313BHK106.0 sqm461.2 sqm1
F-0102Tower 312BHK80.5 sqm344.9 sqm1
F-0103Tower 313BHK104.0 sqm455.8 sqm1
F-0104Tower 313BHK106.0 sqm461.2 sqm1
F-0105Tower 312BHK80.5 sqm344.9 sqm1
F-0106Tower 313BHK106.0 sqm461.2 sqm1

What the numbers tell you

Synthesis from the official RERA scale, unit register, and land rows — the read a sales team won't volunteer.

Unit formatAverage official carpet area is ~1,134 sqft — mid-format homes (2–3BHK territory), not compact stock. This is a boutique, low-density project — 132 homes across 1 tower. Carpet is the RERA-defined usable area, so compare it against the 'super built-up' a broker quotes (typically 25–35% larger).
ParkingThe project declares 143 parking spaces for 132 homes (~1.1 per home) — about one space per home — adequate but tight if you have two cars.
Your land share (UDS)Undivided land share averages ~457 sqm per home; across all 132 homes that is ~341% of the plot — unusually high — likely an extraction artefact; verify the UDS figures against your draft deed. Low UDS relative to land can mean the builder keeps land value the flat owners think they're buying.

🔒 Unit-by-unit guidance · Unit Guidance report

Which block and unit to prefer, the livability read on the filed plans, and a plan-by-plan walkthrough — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full records — land title, amenities paperwork & document catalog · Compliance report

The complete land-title chain, the paperwork behind each declared amenity, and every document row on file with the regulator — the raw records the compliance read is built on.

Unlock in the ₹999 report →

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

8 of 39 compliance document slots are filed as Not Applicable; the remaining 31 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Dec 2025, extended (Section 6 Extension) to 15 Jul 2026 — both dates have passed with no OC on file. The extension on file was granted on 20 Jan 2026 (K-RERA extension no. EX/PRM/KA/RERA/1251/446/PR/260120/006662) — it has been used, its deadline has also passed, and no further extension is recorded.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (BESCOM)
Water & sewage (BWSSB/KWSSB)✓ On file (BWSSB)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including Fire NOC and pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Note environmental clearance is not among the approvals K-RERA marks applicable to this project — if the named-approvals check shows it as "not found in catalog", that is why; ask the builder directly whether it applies here. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

4 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved07-12-2012BWSSB - NOC.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved20-12-2012KSPCB NOC.pdf
KPTCL- BESCOMApproved26-02-2013Bescom - NOC.pdf
Fire and SafetyApproved23-12-2011Fire Force - NOC.pdf
Airport Authority of IndiaApproved19-08-2011HAL - NOC.pdf
BSNL/Telecommunication DepartmentApproved15-09-2011BSNL - NOC.pdf

Project team & certifications

RERA filing

K-RERA names 3 project professional/vendor rows across Architect, Contractor, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectVishal Pujar-2009G Block, Sahakarnagar
ContractorAssociated Constructions-1997BHIG-D 5th Phase, Yelahanka
Structural engineerDhruvaraj---

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2025-Q4): ₹39.22 Cr collected from buyers, ₹35.65 Cr withdrawn from the project's escrow account.

Construction progress80% → 85% (+5 pts)
Units sold/booked as registered107/132 (81%)
Buyer collections in available QPRs₹79.95 Cr
Escrow withdrawals in available QPRs₹59.40 Cr (0.74x collections)

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹81.1 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: HDFC Kasturba Gandhi Marg (IFSC HDFC0000009, a/c …9000). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit.

Location & Connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bellandur–Marathahalli belt2 km
Electronic City9 km
MG Road / city centre9 km
Whitefield IT hub10 km
Outer Ring Road / Manyata15 km
Kempegowda Int'l Airport31 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Inesa Ventures.

Other RERA-registered projects in Bellandur

Major developers building in Bellandur

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in DNR Arista Phase 2?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 27 Jul 2026