GOVIANU ACE GRAND

Bengaluru East · Mahesh G

Project Review · example purchase

Spending a few crores on a home? ₹4,999 to check what you’re buying.

Check what the plans put beside your home, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

From another project · Prestige Park Grove

Avoid bad decisions, only go for the best homes.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
Prestige Park Grove Project Review · first page
First page of the complete sample.
15 Aug 2017declared completionK-RERA registration · read 25 Oct 2026
31registered unitsK-RERA registration · read 25 Oct 2026

Free project details

Registration read 25 Oct 2026

Registered units and project size

Filed categories, unchanged · K-RERA registration · read 25 Oct 2026

The whole registration

0.3registered acres

116.8registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual unit.

RERA details for GOVIANU ACE GRAND

K-RERA · PRM/KA/RERA/1251/446/PR/180425/001545

Project facts and comparisons

On the register

Declared completion15 August 2017
Land area1,074 sq m (0.3 acres)
Homes registered31
Tower/wing entries1

In context

Density116.8 homes per acre
Density in context93rd percentile of 1123 Bengaluru East projects (median 75.5)

Source: K-RERA. Each comparison names the group of projects used.

Project areas, parking and inventory

Project areas and parking

RERA filing
DisclosureOfficial valueWhy it matters
Registered units31Total inventory registered with K-RERA.
Registered land area1,074 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.5Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)31Separate filed counts; these categories may overlap and are not added together.
Open-parking field5Separate filed counts; these categories may overlap and are not added together.
Garage field30Separate filed counts; these categories may overlap and are not added together.
Project start date01-01-2016

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
GOVIANU ACE GRAND33131-

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

Litigation status was not supplied in the captured record. This is not confirmation that there are no cases.

5 of 10 compliance document slots are filed as Not Applicable; the remaining 5 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 15 Aug 2017 — which has passed with no OC on file.

Approval documents

Electricity (BESCOM/ESCOM)Not identified in the document list
Water & sewage (BWSSB/KWSSB)Not identified in the document list
Fire NOCNot identified in the document list
Pollution control (KSPCB)Not identified in the document list
Environmental clearanceNot identified in the document list
Airport Authority height clearanceNot identified in the document list

A listed file does not confirm approval. An unlisted file does not establish that an approval is missing or required. Check the documents and their applicability before relying on them.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

Builder track record

RERA filing

Mahesh has 11 other K-RERA-registered projects in our records (average reported construction progress 40%). 2 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹16.1 lakhs per unit — the developer's own declared construction/development cost, not a unit agreement or asking price. This project-cost average cannot establish whether a quoted unit price is fair. Compare the exact unit, area basis, date and included charges in any price evidence.

RERA 70% project account is on file: INDUSIND BANK sadashivanagar. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest of the listed job hubs is about 9 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
MG Road / city centre9 km
Outer Ring Road / Manyata9 km
Bellandur–Marathahalli belt19 km
Whitefield IT hub24 km
Electronic City24 km
Kempegowda Int'l Airport27 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Mahesh. View Mahesh's full track record →
Mahesh has 12 projects registered in Bangalore.
1 complaints on the K-RERA register against Mahesh in Bangalore.

Other projects by this builder in Bangalore

GM Govianu
Filing overdue · 40% built · 52% sold
Govianu Gurikar Luxuria
No filings
Govianu Jodidhar Atlantis
No filings

Other RERA-registered projects in Yeswanthpur

Major developers building in Yeswanthpur

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.